jonathan.berliner@LIGO.ORG - posted 22:10, Wednesday 02 November 2011 (1658)
Wednesday Ops Log

- EY: BSC6 H2 ETMY ISI craned on to test stand after cleaning by Kris and the crew.

- Many SUS visitors on site for fiber welding.

- Swagelok delivery for Hugh. Praxair delivery at 4:15pm at MY LN tank.

- TMS work ongoing at EY, CraigC and ChrisG assisting.

- PeterK, BennoW, and AEI/LZH group assisting with PSL installation

- Sam Waldman and squeezers continue investigating H1 OMC issues. Squeezers locked H1 this evening, LVEA in laser hazard.

- Two Control Room projectors need their bulbs replaced.