Giles, Travis, Danny, Jason Today, after a few false starts*, the remaining 2 fibers were welded onto the ITMy After annealing, it was successfully hanging. The pitch error of the ITMy was found to be 2.17mRad up. The separation between the ITMy and PUM was measured to be 601.5mm (expecting 602mm). *2 fibers were removed as the first welds were poorly aligned.