LVEA Laser safe
Alarms: Dust in Vac Prep Lab, Diode Room, and CDS frontends
Apollo – Installing walking plates at BSC3
Doug – Shooting alignment of the Elliptical Baffle in BSC2
Richard – Pulling cables at End-Y
09:20 Gerardo working on BOSEMs and Cable Brackets in SUS Cleanroom in LVEA
09:30 Rick & Peter working in the H2-PSL enclosure
10:37 Alexa – To End-X working in VEA
13:10 Patrick working on Dust Monitor #15 calibration failures
Getting continual low level (100 to 150 counts) dust alarms during the day from the Diode Room. Rick S. and I looked in the chiller anti-room, the diode room, and the A/C system, but could not find an apparent source for the alarms. Further investigation is needed to find the source of these alarms.