DGR Storage Building Progress
The stem wall pour is completed, forms are stripped and it has been entirely back-filled. Weather has prevented the pour of the slab this week so Jake has shifted his attention to erecting the metal framework of the building. The forecast is not favorable for a slab pour tomorrow, so its likely to take place early next week.

T. Guidry