TITLE: 04/15 Day Shift: 1430-2330 UTC (0730-1630 PST), all times posted in UTC
STATE of H1: Planned Engineering
INCOMING OPERATOR: None
SHIFT SUMMARY:
ISI is installed , but more work need to be completed before Optics can be installed.
PSL & SPI team are still in the PSL & anti Room, they have installed a beam splitter nut more work may be required.
Jason setup some Faro equipment.
Vacuum team started to pump down the BSC8 annulus door volume.
LOG:
Start Time | System | Name | Location | Lazer_Haz | Task | Time End |
---|---|---|---|---|---|---|
14:32 | FAC | Randy | LVEA | N | HAM1 Heavy lift Prep | 13:32 |
14:33 | FAC | Kim & Nellie | LVEA | N | Technical Cleaning & Supplies, Kim Out early | 16:25 |
14:54 | FAC | Eric | LVEA | N | Checking HVAC zone conditions | 14:57 |
15:02 | FAC | Eric | End X | N | Replacing Sensor | 15:43 |
15:17 | FAC | Christina | Staging | N | Moving Folklifts & matierals | 16:17 |
15:32 | Safety | Richard | LVEA | N | Settign up HAM1 Work Cam | 16:54 |
15:33 | VAC | Jordan | LVEA | N | Purge Air Checks. | 16:01 |
16:06 | EE | Marc | CER | N | Getting chassis for testing. | 16:09 |
16:11 | EE | Marc | EX & Y | N | Power supply testing | 17:25 |
16:15 | VAC | Travis & Jordan | LVEA | N | Closing GV7 and pump work | 17:15 |
16:22 | SPI | Jeff, Jason, Sina, RyanS, Josh | optics Lab , PSL | Yes | Installing SPI Optics, Jeff Out Early | 19:20 |
16:24 | SUS | Camilla & Matt | HAM5 | N | Pulling off First Contact off optics | 16:53 |
16:41 | SAFE T | McCarthy | LVEA | N | Running parts and Safety checks | 18:56 |
16:42 | SEI | Betsy | LVEA | N | Running parts | 20:28 |
16:49 | FAC | Nellie | Mid X | N | Tech cleaning | 17:20 |
16:54 | SEI | Jim, Randy Mitchell, TJ | LVEA | N | SEI Crew flying in an ISI | 18:07 |
17:20 | FAC | Kim | MY | N | Technical Cleaning | 18:35 |
17:24 | ISC | Dainel | LVEA | N | verifing Equipment in the ISC racks | 20:06 |
17:30 | FAC | Eric | PSL adjacent | N | Talking to Jason. | 18:12 |
18:04 | VAC | Jordan | LVEA | N | Preping Y arm RGA | 20:00 |
18:09 | VAC | Travis | BSC8 | N | Checking the anulus pump by ITMY | 18:16 |
18:21 | FAC | Christina | Water tank area & Recycling | Forklifting & dump run | 19:19 | |
18:21 | AOS | Camilla, Matt | LVEA | N | Pulling off first contact by HAM5 | 18:51 |
18:58 | SEI | Jim, TJ, Tyler, Randy, Mitchell | LVEA HAM1 | N | ISI Installation | 00:58 |
18:59 | SEI | Brian | LVEA HAM1 | N | Watching HAM1 Installation. | 21:03 |
19:51 | Safe T | Richard | LVEA | N | Safety checks. | 23:06 |
20:09 | VAC | Jordan | LVEA | N | Pump & RGA checks & bake out | 22:54 |
20:14 | PSL & SPI | Ryan S, Josh, Sina | PSL | YES | Installing SPI Pickoff of the ALS pickoff. | 00:14 |
20:16 | ISC | Camilla & Matt | HAM5&6 | N | cleaning parts | 23:49 |
20:46 | PCAL | Tony | PCal Lab | N | Delivery | 20:50 |
21:09 | ISI | Betsy | LVEA | N | Checking on the ISI team | 22:37 |
21:33 | VAC | Travis | LVEA | N | Table sneaking | 21:49 |
21:40 | IAS | Jason | West bay | N | Staging Faro Equipment | 23:40 |