TITLE: 04/16 Day Shift: 1430-2330 UTC (0730-1630 PST), all times posted in UTC
STATE of H1: Planned Engineering
OUTGOING OPERATOR: None
CURRENT ENVIRONMENT:
SEI_ENV state: MAINTENANCE
Wind: 12mph Gusts, 8mph 3min avg
Primary useism: 0.03 μm/s
Secondary useism: 0.31 μm/s
QUICK SUMMARY:
Beautiful morning to ya, we've got lots of activies to do today!
- Cleanup high bay area to put everything back!
- HAM1 ISI install continuing, remove tooling, get to breaking point for Stand down
- HAM1 cable work in chamber
- HAM1 ISC prep - check all removed cables for loose screws, continued
- VAC - Feedthru Swap, mostly done except 1-2 small ones
- RANDY - Crane 3IFO Flange crate over BT to first stop West Bay for later X-Arm traverse
- ISC Rack work for HAM1 components. Rack will be powered down at times - Marc
- PSL/FIL - Moving picomotor driver, pull cables
Overflow from yesterday's work that may be need to be finished?
- SPI in PSL - add ALS pickoff mirror
- HAM1 ISC prep - Inspect Optics and beam dumps, FC if needed, continued
- BRIAN/ EDGARD/ KISSEL / OLI- Model work on SR3, continue commissioning
- BSC8 Annulus door volume pumping
- EX and EY - ALS work beam profiling (Reqires LAZER HAZ at End VEAs)