ibrahim.abouelfettouh@LIGO.ORG - posted 22:20, Monday 15 September 2025 - last comment - 11:07, Tuesday 16 September 2025(86955)
Post Outage Thermalized NLN BroadBand Calibration

Start Time: 1442034629

End Time: 1442034940

 

2025-09-15 22:15:22,374 bb measurement complete.
2025-09-15 22:15:22,375 bb output: /ligo/groups/cal/H1/measurements/PCALY2DARM_BB/PCALY2DARM_BB_20250916T051011Z.xml
2025-09-15 22:15:22,375 all measurements complete

Images attached to this report
Comments related to this report
elenna.capote@LIGO.ORG - 11:07, Tuesday 16 September 2025 (86963)

Here is the pcal broadband compared to the broadband taken after we pushed the calibration on 8/28. Overall looks ok.