TITLE: 10/16 Day Shift: 1430-2330 UTC (0730-1630 PST), all times posted in UTC
STATE of H1: Lock Acquisition
OUTGOING OPERATOR: Ibrahim
CURRENT ENVIRONMENT:
SEI_ENV state: CALM
Wind: 3mph Gusts, 2mph 3min avg
Primary useism: 0.01 μm/s
Secondary useism: 0.14 μm/s
QUICK SUMMARY:
- 15:30 -> 19:00 UTC Planned calibration measurement followed by comissioning, we are going to move the beam spot to it's previous position before running the calibration measurement.
- We're relocking and TR_CARM following a 13:01 UTC lockloss
- We've had 1 short lock since the earthquake this morning, 6.5 from Indonesia
- Stand down query failure, I'll restart this
Locklosses aren't updating again, it didn't catch the one this morning at 13:01. The DARM fom has timed out three times this morning as well (tagging CDS).
15:30 UTC The PI around 10.2kHz rung up but damped back down, it was smaller than the last 3 times we witnessed it since maintenance.