TITLE: 11/05 Day Shift: 1530-0030 UTC (0730-1630 PST), all times posted in UTC
STATE of H1: Preventive Maintenance
INCOMING OPERATOR: Corey
SHIFT SUMMARY: Maintenance Tuesday. Relocking hasn't been very successful so far. CO2Y was having IR faulting issues (alog87952), then we had a lock loss that occurred when we got to the Close_Beam_Diverters state, which we saw last week (alog87877). Now we are having a few earthquakes rolling through as we sit in max power. We don't want to advance until the ground stop shaking a bit so we can keep high gain asc on.
LOG:
| Start Time | System | Name | Location | Lazer_Haz | Task | Time End |
|---|---|---|---|---|---|---|
| 16:06 | ISC | Matt | CR | n | IMC 60W meas. | 17:01 |
| 16:07 | SYS | Mitchell, Randy | LVEA | n | Mega cleanroom sock install | 17:15 |
| 16:10 | FAC | Kim, Nellie | LVEA | n | Tech clean | 18:03 |
| 16:11 | VAC | Jordan, Travis, Janos | EY | n | Purge air line install | 19:59 |
| 16:12 | VAC | Gerardo | LVEA, Mech room | n | Run Kobelco, pump CP1 LN2 line, test turbo pumps | 20:35 |
| 16:12 | CDS | Betsy | CER | n | Putting stickers on racks | 16:23 |
| 16:20 | FAC | Tyler, Rays | Site | n | Septic tank inspection and pumping | 17:59 |
| 16:22 | CDS | Fil | EX | n | Connecting fibers to prep for RFM test | 17:27 |
| 16:31 | PCAL | Dripta, Tony | PCAL lab | LOCAL | Check on lab | 16:47 |
| 16:38 | SYS | Betsy | LVEA | n | Check on sock and domes | 17:14 |
| 16:44 | VAC | Norco | CP1 | n | LN2 fill | 18:49 |
| 16:44 | FAC | Chirs, pest | LVEA, outbuildings | n | Pest control | 17:49 |
| 16:49 | PCAL | Tony, Dripta | EX | YES | PCAL calibration meas. | 19:31 |
| 17:07 | CDS | Betsy | CER | n | Removing stickers from ISCC3&4 | 17:16 |
| 17:17 | VAC | Norco | CP5 MX | n | LN2 fill | 19:14 |
| 17:31 | CDS | Fil | LVEA | n | Cable pull around HAM2/3 | 20:05 |
| 17:34 | - | Richard | LVEA | n | Checking on a few things | 17:57 |
| 17:34 | SUS | Oli | CR | n | PRM, SRM estimator measurements | 20:08 |
| 17:40 | PEM | Robert, Sam | LVEA | n | Mounting accel. | 18:49 |
| 17:45 | SYS | Randy | LVEA | n | Taking measurements of HAM3 and BSC2 areas | 18:27 |
| 17:49 | FAC | Chris | LVEA | n | FAMIS checks | 18:32 |
| 17:49 | PSL | Jason | LVEA | n | Walking the PSL chiller lines, FAMIS | 18:01 |
| 17:57 | SQZ | Sheila, Matt | CR | n | OM2 hot OMC meas. | 20:08 |
| 17:59 | FAC | Tyler, Geotech | MY | n | CEBEX surverying | 23:24 |
| 18:03 | FAC | Kim | EX | yes | Tech clean | 19:17 |
| 18:04 | FAC | Nellie | EY | n | Tech clean | 19:20 |
| 18:05 | CDS | Erik | EY, EX | n | Grabbing equipment from EY, doing RFM test at EX | 19:18 |
| 18:13 | CDS | Marc | LVEA | n | Helping Fil with cables at HAM2/3 | 20:05 |
| 18:14 | IO | Rahul | Opt Lab | LOCAL | JAC testing | 19:07 |
| 18:55 | PEM | Robert, Sam | LVEA | n | More accelerometer moving | 20:28 |
| 19:20 | FAC | Rana, Mike, Tour | LVEA | n | Tour | 20:12 |
| 19:41 | FAC | Kim | FCES | n | Tech clean | 19:42 |
| 19:51 | FAC | Randy | XTube | n | Filling cracks | 23:02 |
| 20:47 | PCAL | Tony | PCAL lab | LOCAL | Wrapping up meas. | 21:32 |
| 20:52 | TCS | Ryan C | LVEA | n | Turn TCS CO2Y back on | 20:53 |
| 20:58 | PCAL | Rene, Alicia | PCAL lab | LOCAL | Check out lab with Tony | 21:44 |
| 21:09 | TCS | TJ | LVEA | N | Reset CO2Y laser | 21:24 |
| 22:19 | SPI | Corey, Ryan S | Opt Lab | n | Optics cleaning | 23:29 |
| 23:04 | PEM | Robert, Sam | Arms | n | BTE cell phone signal testing | 02:04 |