Gerardo, Jordan, Travis
Today, we finished the installation of the replacement purge air piping at EY. The system still needs to be tested for gross leaks, new filter elements on the supply line installed, an additional support added to the mechanical room side of the purge piping, and the new compressor and purge line validated via FTIR testing. We plan to finish these installations and tests in the next week or two.