corey.gray@LIGO.ORG - posted 16:29, Wednesday 03 December 2025 (88330)
Wed DAY Ops Summary

TITLE: 12/03 Day Shift: 1530-0030 UTC (0730-1630 PST), all times posted in UTC
STATE of H1: Planned Engineering
INCOMING OPERATOR: None
SHIFT SUMMARY:

Main goal for today was to continue to see troubleshoot H1 to see if it survived the CDS work from earlier this week (by trying to get H1 back to NLN)---Elenna and Sheila worked on this.  There continued to be issues with ASC SRC---Elenna said this is common for H1 recoveries.  Sheila also mentioned that the alignment issue most likely is a result of Gate Valve closures affecting the Green Camera alignment.

Recovery work above had to wait until about 11amPDT due to remaining LVEA crane inspections.  

During Recovery work 20-bit DAC card was swapped out for one which was installed yesterday that had issues.
LOG: