TITLE: 12/04 Day Shift: 1530-0030 UTC (0730-1630 PST), all times posted in UTC
STATE of H1: Planned Engineering
INCOMING OPERATOR: None
SHIFT SUMMARY:
After CDS & H1-Locking work of yesterday, today we transitioned to starting prep work for the upcoming vent of HAM7.
However, there was more CDS work today which was related to ISC Slow Controls....but in the middle of this...
There was a 90min power outage on site!!
LOG:
Recovery milestones:
22:02 Power back-up
22:04 CDS / GC seeing what's on/functional, then bring infrastructure back up
22:10 VAC team starts Kebelco to support the ar pressure that's keeping the cornerstation gate valves for closing
22:13 Phones are back
22:17 LHO GC Internet's back
22:25 GC wifi back up, alog and CDS back up
22:40 RyanS, Jason, Patick got PSL beckoff back up
22:55 VAC in LVEA/FCES back up
22:57 CDS back up (only controls)
23:27 PSL computer back
00:14 Safety interlock is back
00:14 HV and ALSY on at EY
00:35 opslogin0 back up
00:37 CS HV back up
00:53 CS HEPI pump station controller back up
01:05 CO2X and CO2Y back up
01:10 HV and ALSY on at EY
01:22 PSL is alive
Note: EY 24MHz oscillator had to be power cycled to resync
Casualties:
- lost ADC on seiH16
- 18V power supply failure at EY in SUS rack
Log:
| Start Time | System | Name | Location | Lazer_Haz | Task | Time End |
|---|---|---|---|---|---|---|
| 22:32 | VAC | Gerardo | MX, EX, MY, EY | n | Bringing back VAC computers | 23:41 |
| 23:32 | VAC | Jordan | LVEA, FCES | n | Bringing back VAC computers | 22:55 |
| 22:54 | PSL | RyanS, Jason | LVEA | n | Turning PSL chiller back on | 23:27 |
| 23:03 | VAC | Jordan | LVEA | n | Checking out VAC computer | 23:41 |
| 23:56 | SAF | Richard | EY | n | Looking at safety system | 00:25 |
| 00:02 | JAC | Jennie | JOAT, OpticsLab | n | Putting components on table | 01:24 |
| 00:19 | SAF | TJ | EX | n | Turning on HV and ALSX | 00:49 |
| 00:38 | TCS | RyanC | LVEA | n | Turning CO2 lasers back on | 01:06 |
| 01:03 | EE | Marc | CER | n | Power cycling io chassis | 01:14 |
| 01:06 | PSL | RyanS, Jason | LVEA | n | Checking makeup air for PSL | 01:10 |
| 01:07 | JAC | Jennie | LVEA | n | Grabbing parts | 01:14 |
| 01:08 | beckhoff | patrick | cr | - | BRSx recovery | 02:20 |
| 01:08 | sei | jim | EX.EY | - | HEPI pump station recovery | 01:58 |
| 01:25 | SEI | Patrick | EX | n | BRSX troubleshooting | 01:54 |
| 01:27 | EE | Marc | EX | n | Looking at RF sources | 02:09 |
| 02:00 | EE | Fil | EY | n | Power cycling SUSEY | 02:19 |
| 02:09 | VAC | Gerardo | MX | N | Troubleshooting VAC computer | 02:27 |
| 02:12 | EE | Marc | CER | N | Checking power supplies | 02:16 |
Since Oli's alog, I tried to keep a rough outline of the goings-on:
Marc and Fil went down to EY to replace the failed power supply, which brought life back to the EY frondends.
Dave noticed several models across site had timing errors, so he restarted them.
Gerardo continued to torubleshoot VAC computers at the mid-stations.
Once CDS boots were finished, I brought all suspension Guardians to either ALIGNED or MISALIGNED so that they're damped overnight.
I started to recover some of the Guardian nodes that didn't come up initially. When TJ started the Guardian service earlier, it took a very long time, but most of the nodes came up and he put them into good states for the night. The ones that didn't come up (still white on the GRD overview screen) I've been able to revive with a 'guardctrl restart' command, but I can only do a couple at a time or else the process times out. Even this way, the nodes take several minutes to come online. I got through many of the dead nodes, but I did not finish as I am very tired.
Main things still to do for recovery: (off the top of my head)