Per WP 12926
GV-7 & GV-5 hard closed at 14:16 PST and 14:34 PST respectively. Metal valve to gate annulus opened as well.
PT-114 and PT-134 pirani interlocks tripped while I was nearby opening the annulus valves. I have re-renabled them from the control room.
FC-V3 (BSC3) and FC-V4 closed as well to isolate the FCT.
Plot of PT-120B (BSC2), PT-124B (CP-1) and PT-144B (CP-2) during valve closure attached.