IFO is IDLE in ENGINEERING
The LVEA has just been transitioned to LASER HAZARD following the venting of the Relay Tube.
Vent work continues with the following progress:
- LVEA Laser Hazard Transition - DONE
- HAM1 - Set irises on table to capture PSL beam pointing - ONGOING
- HAM1 - Go into PSL and add lenses -AFTERNOON
- HAM7 - Start deinstall relay tube, install viewport adapter on HAM5 side - AFTERNOON
- HAM7 - In-chamber OPO work continued - AFTERNOON
- HAM1 - Load in/stage all JAC hardware, plug in JM1 and JM3 to start testing controls - AFTERNOON
- HAM1 - Install periscopes - ONGOING
- BSC2 - FARO work - ONGOING
Other:
- DAQ Restart 10:18 PT to 10:57 PT
- There is a vacuum pump running near HAM7 reni
- Craning work in north bay LVEA
- Jeff and Oli working on SUS models
Ryan S will take over ops shift for the next few hours.