Betsy, Fil, Rahul
Today we kicked started the installation activities in HAM1 chamber for the Jitter Attenuation Cavity (JAC). Given below are the things we placed on the ISI table - they are all roughly positioned and dog clamped.
1. Tip Tilt JM1 - now connected to electronics chain, having some issues with the bosem adc counts etc, will continue looking into it.
2. Tip Tilt JM3 - now connected to the electronics chain, bosem centered, will proceed for health checks once the chassis and electronics chain looks okay.
3. The two periscopes for the JAC, Type 121 and 132 - assembly report posted by Jennie - 88574.
4. Some optics on Siskiyou mount were also added to the table.
I am attaching pictures which shows the above mentioned things added to the table - and for comparison a picture showing before any addition was (here) made.
Fil also performed group loop checks on JM1 and JM3 and did not find any issues with them.
EPO-Tagging for JAC installation