Reports until 12:02, Friday 02 January 2026
LHO General
richard.mccarthy@LIGO.ORG - posted 12:02, Friday 02 January 2026 (88673)
First site inspection of the new year.

Site Walk Through 2 Jan 2026

LExC is in great shape no indication of problems.

Staging building is in good shape.

VPW two ovens running and in the parameters that Chris told us.  Weld shop temperature was fine so no pipe issues.

LSB looks fine.  Tyler was in his office

OSB/LVEA everything was in order.  Kobelco running door covers billowing slightly.  No signs of problems.

Mid and Ends were fine.  

Carpenter shop/ water room fire pump room and electrical room were all fine.

FCES in great shape.  

I leave the site with, Tyler clearing a path to EX for LN2 delivery.  I am his phone buddy.