TITLE: 01/27 Day Shift: 1530-0030 UTC (0730-1630 PST), all times posted in UTC
STATE of H1: Planned Engineering
INCOMING OPERATOR: None
SHIFT SUMMARY:
A very productive day with the following activities:
1. EOM - Work continued on the EOM in the Optics Lab.
2. HAM1 - MC Trans has been recovered! Meaning that light has been aligned from the input through the JAC to the Mode Cleaner!
3. HAM7 - OPO work is continuing.
4. VAC - Relay tube work ongoing.
LOG:
| Start Time | System | Name | Location | Lazer_Haz | Task | Time End |
|---|---|---|---|---|---|---|
| 22:49 | SAF | LVEA IS LASER HAZARD | LVEA | YES | LVEA IS LASER HAZARD \u0d26\u0d4d\u0d26\u0d3f(\u239a_\u239a) | 16:49 |
| 15:57 | FAC | Kim, Nellie | LVEA | Y | Technical Cleaning' | 16:19 |
| 16:49 | OPS | Corey | Optics Lab | N | Part Search | 17:03 |
| 16:58 | FAC | Kim, Nellie | LVEA | Y | Technical Cleaning | 17:49 |
| 17:19 | FAC | Randy | LVEA | Y | BSC2 Platofrm Work | 18:44 |
| 17:23 | COC | Keita | Optics Lab | N | EOM Work | 20:22 |
| 17:35 | VAC | Travis, Jordan | LVEA | Y | Relay Tube Work | 19:30 |
| 17:46 | SQZ | Jennie | LVEA | Y | Opening PSL Light Pipe | 17:48 |
| 18:12 | SUS | Betsy | LVEA | Y | HAM7 OPO | 22:29 |
| 18:12 | SUS | Rahul | LVEA | Y | HAM7 OPO | 21:51 |
| 18:23 | COC | Jennie | LVEA | Y | HAM1 | 21:51 |
| 18:49 | FAC | Randy | LVEA | Y | HAM7 Help | 19:31 |
| 18:59 | JAC | Elenna | Opt Lab | N | EOM work | 19:59 |
| 19:12 | OPS | Corey | Optics Lab | N | Parts | 19:23 |
| 19:27 | ISC | Matt | Vac-Prep/JOAT Lab | N | Checking on laser | 21:51 |
| 19:42 | SUS | Kar Meng | LVEA | Y | HAM7 | 18:42 |
| 21:35 | PCAL | Tony | PCAL Lab | N | Meas. prep | 23:34 |
| 21:52 | COC | Keita, Elenna | Optics Lab | N | EOM | 23:40 |
| 22:18 | ISC | Matt, Sophie | Vac-Prep, JOAT | N | Checking on laser (CHETA) | 22:34 |
| 22:19 | SQZ | Sheila | LVEA | Y | HAM7 | 18:19 |
| 22:20 | VAC | Gerardo, Jordan | MY | N | Part Grab | 23:53 |
| 22:22 | SUS | Rahul | LVEA | Y | HAM1/7 | 22:29 |
| 22:40 | EE | Fil | LVEA | Y | HAM6 Rack Work | 01:40 |
| 23:09 | SUS | Rahul, Sheila, Jennie | LVEA | Y | HAM1 Work | 02:09 |
| 23:10 | ISC | Matt, Sophie | Vac-Prep, JOAT | N | CHETA | 01:10 |
| 23:27 | SAF | Jenne D | Input arm | Look at Ham2 Ham3 layoutg | 23:53 | |
| 23:47 | SUS | Betsy | LVEA | N | HAM1 | 01:47 |