TITLE: 02/09 Day Shift: 1530-0030 UTC (0730-1630 PST), all times posted in UTC
STATE of H1: Planned Engineering
INCOMING OPERATOR: None
SHIFT SUMMARY:
HAM7 had viewports inspected and steps initiated for pumping down. JAC team spent a good part of the day inspecting the in-vac EOM output beam. The ACCESS SYSTEM computer had its network issues fixed (for Access System & cameras).
LOG:
- 1531-1547 Optics lab clean (kim)
- 1703-1803 Return for main cleaning in lvea (kim)
- 1803-1859 Picking up garb at Receiving and cleaning our buggy MidY (kim)
- 1900-1931 MX cleaning (kim)
- 1733-1756 Looking for ground seismometer at end stations (jim)
- 1825-1945 HAM7 Annulus Ion Pump (AIP) pumping begins (gerardo)
- 1837-2050 JAC EOM checks (jennie, jason)
- 1847-1913 HAM3 taken to ISI_DAMPED_HEPI_OFFLINE (from ISOLATED) to allow crawling around the chamber to look at feedthrus (jim, betsy)
- Jim out and HAM3 returned to ISOLATED. Betsy working with Travis.
- 1851 HAM3 + HAM7 AIP pumpdown checks (travis)
- 2000-2008 increasing PSL power for JAC (ryanS)
- 2019 another adjustment (RyanS)
- 2117 VAC team return to work on HAM7 for AIP pumpdown, viewport inspection, chamber pumpdown (travis, gerardo, jordan)
- 2139 Out to HAM7 (betsy,richard)
- 2203--0025 Back to HAM1 for JAC EOM checks (keita, jason, jennie)
- They mentioned issues with one of the platforms at HAM1 to Richard.
- 2207-2315 Checking VAC cable at EX (marc)
- 2250 Organizing parts in optics lab (camilla)
- 2233 swapping spheres in PCal Lab (tony)
- 2353 Dropping parts off at MY (travis)
- 2357-0012 Maggie giving a tour to intern applicant
- 0012-0019 Rack photos (oli)
- 0025 VAC team (gerardo,jordan) preparing for roughing pump at HAM7.
- I confirmed that the picomotor "Squeezer Things" are DISABLED via picomotor medms.