TITLE: 06/09 Day Shift: 1430-2330 UTC (0730-1630 PST), all times posted in UTC
STATE of H1: Planned Engineering
INCOMING OPERATOR: None
SHIFT SUMMARY:
With ISS alignment progress, able to let SPI work start, transition the LVEA to SAFE to allow BSC2 HEPI spring work to start. HAM7 in-chamber work continued (in a bifurcated laser hazard state). CRS work in the optics lab and CRS Lab.
LOG:
- Before1430-1547 Technical cleaning and supply checks in the lvea (kim)
- 1626-1749 Back to LVEA (kim)
- 1501- ~1630 LN2 truck (Pacific CA Systems) arrives & goes to CP2 Dewar
- 1518 Testing out new Reservation System on nuc30--to help prevent crashes (tj)
- ~1605 Crashed & had permission issues; tj notified.
- ~1715 About when ReservationSystem returned to service
- 1530 Pest control person had issues with gate, so I opended for them
- 1532-1927 First Contact pour begins (ibrahim.anamaria)
- 1555-1751 Betsy joining,
- 1636 ryanS joining
- 1744 anamaria out for a break & went back in
- 1539-1836 Taking photos out at HAM2 (keita.rahul); 1632 disha joins
- 1836 out; seeing flashing from Faraday and would like to talk to sheila about it.
- 1641-1750 Sitewide FAMIS maintenance (chris)
- 1750-1819 LVEA FAMIS checks (chris)
- 1647-1707 Moving a box in West Bay (randy)
- 1657-1925 HAM7 in-chamber (camilla.sheila)
- 1659-1940 Setting up FARO @HAM3 for BSC2 (jason.ryanC)
- 1725-1740 Grabbing wrench from CRS lab (jim)
- 1726 checking HEPI at Mechanical Room + MY for parts (fil)
- 1735-1914 lvea tour (thomasR)
- 1740-1801 turning off turbo @EY (jordan)
- 1745-1929 CRS work (alexandra)
- 1748-1940 Set-up for BSC2 HEPI (jim,mitch)
- 1748 3ifo checks at LVEA + mids (tyler)
- 1805 LSB then quick Staging stop & then off to MY (kim)
- 1805-1929 CRS work (Shoshonna)
- 1815-1927 Back to ITMy First Contact pour (anamaria)
- 1825-1907 Corner HEPI Pump Station work (patrick, fil)
- 1915 OAF DAC (used by PEM) getting checked out (dave, erik)
- 2315 Marc joining erik @cer
- 1955 SPI Install at HAM3 (jeff.jennie.josh)
- 2008-2025 Transition LVEA to SAFE (richard.betsy.keita)
- 2031 cleaning CRS optics in optics lab (alexandra.shoshonna)
- 2032 showing randy work in lvea (jim)
- 2033-2323 BSC2 HEPI + FARO work (jim.mitch. jason.ryanC)
- 2135-2253 tony joining
- 2252 ibrahim joining
- 2036-2116 HAM3 feedthru check (travis)
- 2045 HAM2 clean-up (keita)
- 2054 HAM7 in-chamber work (sheila.ryanS.begum)
- 2100-2225 clean-up for BSC1 first contact (anamaria.ibrahim)
- 2121-2155 Visitor from APS getting a tour from Jenne+Mike
- 2144-2159 handing part off to jim in lvea (randy)
- 2214-2224 Checking on teams in lvea (betsy)
- 2312 ground loop checks for HAM2 at the rack (fil)
- 2313 HAM2 SUS were taken to SAFE (from ALIGNED)