TITLE: 07/01 Day Shift: 1430-2330 UTC (0730-1630 PST), all times posted in UTC
STATE of H1: Planned Engineering
OUTGOING OPERATOR: None
CURRENT ENVIRONMENT:
SEI_ENV state: MAINTENANCE
Wind: 13mph Gusts, 7mph 3min avg
Primary useism: 0.02 μm/s
Secondary useism: 0.11 μm/s
QUICK SUMMARY:
Potential work according to the trello schedule:
BSC2 - Alignment check w/SQZ beam
BS - Re-center OPLEV (Jason)
TUES - BSC2 - ground loop checks and fixes (Fil, Oli, Betsy)
BSC2 - L4C install at dome level (Mitchell, Jim)
TUES - HAM3 - ground loop checks (Fil)
BSC2 & 3 - B&K testing (TJ, Ibrahim, Rahul)
HAM3/BSC2 - In chamber work, after FARO/HEPI work - Suspend, TFs (Ibrahim, Betsy, Oli)
HAM7 - In-chamber SQZ work continued, local laser Haz
Potential CDS work not listed on the trello:
Longer than normal model restarts for PEM, & CRS to include new channels , and new camera channels & maybe some HEPI beckhoff channels.