SHIFT SUMMARY:
Today there was continued work looking at the lead-up to the CARM TO TR step for ISC LOCK. For the most part DRMI reacquisition was fairly easy (Sheila alog-ed about a random PR3 move which was odd.)
Toward the end of the shift, OM3's heater was increased from 1.0 to 4.0W for over the weekend.
LOG:
- 1437-1536 Manual Initial Alignment
- 1700-1740 EQ Mode Activated (M5.8 Russia)
- 1715-1829 CHETA laser hazard work (sophie)
- 1723-1732: PRMI taking a while to lock, so touched up PRM & BS via PRX + MICH DARK align ifo states. (PRM moved the most (in pit), not much though); then back to PRMI_LOCKED.
- 1850-1925 Working on CrystalLaser (tony)
- 1915-1933 IR cavity alignment for PRM, BS, SRM again.
- 1948 While waiting for DRMI to lock, flashes all of sudden stopped. RyanC noticed it was due to
- 2100-2205 OMC dcpd function generator set-up in lvea, WP13679 (keita,alex)
- But mentioned going out later.
- 2122-2209 Recording change made with PCal CrystalLaser (tony, ryanC)
- 2312 Sheila requested us to take SR3's heater to 4.0 W (from 1.0W) for over the weekend.