Displaying reports 1-20 of 86410.Go to page 1 2 3 4 5 6 7 8 9 10 End
Reports until 16:55, Wednesday 28 January 2026
H1 SQZ (EPO)
anthony.sanchez@LIGO.ORG - posted 16:55, Wednesday 28 January 2026 (88878)
Removed a few parts from HAM7

Friday Jan 23rd Sheila, Karmeng, & myself removed 3 Irises, and swapped out a PD for a beam dump.
First Karmeng & I Turnt up the purge air & took pictures of the table.  
Then we found all the irises Sheila wanted to remove:
Iris 1.... which was one of the 3 Sheila wanted to remove along with Iris 2 and Iris3 near by.

We decided to swap a Photodiode for a Beam Dump due to the scattered light documented in this here FRS ticket, as putting a beam dump infront of the PD was not possible due to Space constraints.
Swapping this PD out required some expert level HAM7 Yoga so Shelia did the switcheroo.

I'm sure it will be fine, but the PD was in place to catch light that is there when the IFO is locked.... and well since the IFO wasn't locked... we Eyeballed the placement of that beam dump that took it's place.  So we are fairly sure the Beam Dump is in the right place.  Oh! I took a few before pics of the PD too just to do some comparing with the after pics of the Beam Dump.
We did check all the beam paths in HAM 7, but that last beam dump we can't check so ¯\_(ツ)_/¯ Looked good to us.

Thanks to Jordan for the last minute purge air cram session.

Later!





 

Images attached to this report
H1 General
oli.patane@LIGO.ORG - posted 16:30, Wednesday 28 January 2026 (88950)
Ops Day Shift End

TITLE: 01/29 Day Shift: 1530-0030 UTC (0730-1630 PST), all times posted in UTC
STATE of H1: Planned Engineering
INCOMING OPERATOR: None
SHIFT SUMMARY: The LVEA is LASER HAZARD. Lots of HAM1 and HAM7 work today
LOG:

Start Time System Name Location Lazer_Haz Task Time End
15:36 FAC Randy LVEA YES Taking down cable tray struts using crane 19:23
16:06 FAC Nellie, Kim LVEA YES Tech clean 17:12
17:07 TCS Matt, Sophie JOAT Lab n Installing parts 18:13
17:29 EE Daniel LVEA YES Testing cabling work from yesterday by HAM6 18:42
17:40 FAC Kim, Nellie LVEA YES Tech clean 18:13
17:42 JAC Jennie LVEA YES Catching strays (beams) 18:55
17:46 JAC Jason LVEA YES Helping Jennie, moving rotation stage 20:01
18:13 FAC Kim EX n Tech clean 19:43
18:36   Richard LVEA YES Checking in on Randy 18:49
18:47 JAC Keita OptLab n EOM work 20:56
18:51 PCAL Tony, Dripta EX n PCAL work 20:12
19:07 JAC Elenna OptLab n EOM work 20:56
19:23 JAC Jennie LVEA YES Catching more strays (beams) 20:01
20:38 SPI Jim OptLab n Working on SPI 21:36
21:46 FAC Randy LVEA YES Walkaround 22:33
21:51 JAC Jennie, Jason JOAT Lab n Popping in quickly 22:09
22:08 SQZ/SUS Sheila, Rahul LVEA Y HAM7 work, OPO (Sheila out 23:03) 23:16
22:14 JAC Jason, Masayuki LVEA YES JAC work ongoing
22:17 JAC Betsy, RyanS LVEA YES Dumping beams and moving tables ongoing
22:22 JAC Keita OptLab n EOM work ongoing
22:41 JAC Elenna OptLab n EOM work ongoing
23:05   RyanC, Rahul LVEA YES Moving in table 23:35
23:43 CDS Dave EX n Turning EX HWS computer back on ongoing
H1 CAL
anthony.sanchez@LIGO.ORG - posted 16:16, Wednesday 28 January 2026 (88949)
PCAL TX Module Maintenance.

Yesterday Dripta & I went to the End X Station to do a TX module Maintenance.
The results of this TX Module Maint can be found here T1600436

 

Laser SN01 Incoming laser power from T1300100              
Date 6/4/2013   Aug. 3, 2018 Mar. 19, 2019 Jan-18-2024 April-22-2025 Jan-27-2026  
Laser Shutter Check     PASS PASS Pass Pass Pass  
Max OFS Offset     9.9 V 7.8 V 7.7V 7.7V 7.75  
95% OFS Offset     9.405 V 7.4 V 7.3V 7.315 7.36  
Operating OFS Offset     4.7025 V 3.7 V 3.85V 3.6575 3.68  
Laser Output Power 2.05 W   1.72 W 1.75 W 1.67W 1.7 1.662  
After-Laser Rejected Power     56.5 mW 54 mW 36.6mW 34.6mW 35.7mW  
AOM Input Power     1.60 W 1.69 W 1.59W 1.65 1.64  
Max Diffracted Power     0.967 W 1.13 W 1.1W 1.14 1.1  
Un-Diffracted Power     0.359 W 0.306 W 266mW 0.307W 0.297  
AOM Diffraction Efficiency     60.44% 67% 69.00% 0.690909090909091 0.670731707317073  
After-AOM Rejected Power     12.8 mW 13.7 mW 14.7mW 15.2mW 16.7mW  
TxPD Power     11.1 mW 6.06 mW 6.36mW 11.9mW 6.14mW  
OFSPD Power     5.7 mW 6.56 mW 6.36mW 5.7mW 6.58mW  
Outer Beam Power     228 mW 0.257 W 265mW 0.536 512  
Inner Beam Power     228 mW 0.255 W 260mW 0.526 501  
Output Beam Power Ratio     1 0.992217898832685 0.9811 0.98134328358209 0.978515625  
OFS Gain     38.19 dB 41 dB 39.6db 39.6 39.79  
OFS Phase Margin     60.9 degrees 55 degrees 43deg 42.1 42.3  
ALOG         75484   88949  
                 
Images attached to this report
Non-image files attached to this report
H1 PSL (OpsInfo)
jennifer.wright@LIGO.ORG - posted 13:04, Wednesday 28 January 2026 - last comment - 17:13, Wednesday 28 January 2026(88948)
Input power to HAM1 at 1W

Jennie W, Jason O

 

Jason and I added four beam dumps - two before we turned the power up, two after.

There were no beams leaving the table at 100mW but we dumped two beams going towards the PSL septum plate (one was transmission through JM1).

Jason saw one leaving the table after we were at one watt so this and the transmission throuhg JM3 + JM2 are now dumped.

 

Comments related to this report
jason.oberling@LIGO.ORG - 17:13, Wednesday 28 January 2026 (88951)

PSL power into HAM1 has been returned to ~100mW and the PSL rotation stage is de-energized and locked out once again.

H1 TCS
sophie.muusse@LIGO.ORG - posted 12:04, Wednesday 28 January 2026 (88946)
CHETA Update

S. Muusse, M. Todd


Lens realigned on X-arm CHETA table for corrected focal lengths and the beam profiled which had better agreement with the model. ITM beam size from fit are much closer to ideal beamsize on ITM (≈ 52.7mm).


Fit for profile after L2 vs model 

  Fit Model
w0x,w0y  [um] [970.5 ± 28.7, 940.8 ± 23.3] [1023.9,  981.71]
z0x,z0y [mm] [-1078.1 ± 32.0, -901.9 ± 22.5] [1.046 , 0.928 ]
qx [mm] 1.078 ± 32.0 + 0.643 ± 38j 1.046 + 0.708j 
qy [mm] 0.902 ± 22.5 + 0.604 ± 30j 0.928 + 0.651j 
Beam radii at ITM [mm] [54.442, 55.885]   [52.311, 54.385]

Beam radii at ITM is foudnfrom fit by propagating the fit q to the ITM.

Images attached to this report
H1 ISC
daniel.sigg@LIGO.ORG - posted 11:52, Wednesday 28 January 2026 (88947)
Whitening concentrators installed

We commissioned the 2 whitening concentrators in the ISC-R6 rack, after some of the chassis were rearranged, see alog 88922.

The whitening concentrators control the ASC-AS_C, the OMC_A and the OMC_B QPDs, and will in the future also control the ASC-LO_A and the ASC-LO_B WFS, as well as the ASC-LO_C QPD.

The slow controls software needed to be updated to support this.

All whitening controls channels were verified using the binary IO tester.

LHO VE
david.barker@LIGO.ORG - posted 11:11, Wednesday 28 January 2026 (88945)
Wed CP1 Fill

Wed Jan 28 10:05:11 2026 INFO: Fill completed in 5min 8secs

 

Images attached to this report
H1 CDS
david.barker@LIGO.ORG - posted 09:58, Wednesday 28 January 2026 - last comment - 10:05, Wednesday 28 January 2026(88942)
Tuesday afternoon DAQ restart for Beckhoff slow controls channel change

WP12980 DAQD code upgrade.

Jonathan, Daniel, Dave:

The DAQ was restarted at 16:08 Tue 27jan2026 for Beckhoff ISC-CS changes, applied when Daniel restarted the slow controls system earlier that afternoon. This was an EDC + DAQ restart.

We took this opportunity to complete the upgrade of DAQD on the 1-leg (it has been running on the 0-leg for over a week).

the 0-leg was a standard retstart, the 1-leg was a staggered restart node-by-node to implement the upgrade, followed by a full restart of the 0-leg.

Comments related to this report
david.barker@LIGO.ORG - 10:05, Wednesday 28 January 2026 (88943)

Tue27Jan2026
LOC TIME HOSTNAME     MODEL/REBOOT
16:08:03 h1daqgds0    [DAQ]  <<< 0-leg restart
16:08:10 h1daqfw0     [DAQ]
16:08:10 h1susauxh56 h1edc[DAQ] <<< EDC restart for new Beckhoff channels
16:08:11 h1daqnds0    [DAQ]
16:08:11 h1daqtw0     [DAQ]


16:16:15 h1daqdc1     [DAQ] <<< 1-leg restart, new daqd.
16:16:21 h1daqfw1     [DAQ]
16:16:21 h1daqtw1     [DAQ]
16:16:22 h1daqnds1    [DAQ]
16:16:31 h1daqgds1    [DAQ]
16:17:06 h1daqgds1    [DAQ]
 

H1 ISC
marc.pirello@LIGO.ORG - posted 09:39, Wednesday 28 January 2026 (88925)
JAC EOM Heliax Cable Testing

I tested these in the morning with the Fieldfox TDR and found two of the Heliax terminations were bad on the HAM1 end of the run.  I reterminated them and completed the install to the feedthrough, then took new TDR scans, they are uploaded here.

Images attached to this report
Non-image files attached to this report
H1 SQZ
sheila.dwyer@LIGO.ORG - posted 08:51, Wednesday 28 January 2026 (88939)
clipping of SQZ beam after cable dressing

Yesterday Rahul and I went to HAM7 to try to address the suspension problems reported in 88913.  

I watched the beam on SQZT7 irises in the homodyne path while Rahul moved cables away from the suspended platform, the beam moved as he shifted the cables near the V3/H3 osems (the hard to reach ones) away from the platform, but not so much that we lost the beam.  He also tried lifting the cable connector for the new translation stage on and off the OPO, this had a similar impact on the alignment but we never lost the beam.  

We left the connector as it was, but moved the cables away from the platform.  The beam coming out of the chamber was hitting the top of the upper periscope mirror on SQZT7, clipping somewhat there.  We took the power meter in chamber and measured 20-30% losses between the beam leaving the platform towards the filter cavity and the beam returning in transmission of SFI1, which was pretty consistent with the power measured on SQZT7.  

Jeff re-evaluated the suspension health 88921 yesterday afternoon.  This morning from the control room I moved ZM1 in pitch -1800 urad which seems to have relieved the clipping according to the OPO IR TRANS PD, but has saturated ZM1 pitch.  This can probably be offloaded to A:M3 to relieve the saturation.

H1 SUS (SUS)
rahul.kumar@LIGO.ORG - posted 10:59, Tuesday 27 January 2026 - last comment - 08:37, Wednesday 28 January 2026(88917)
HAM7 OPO health check investigation - took fresh pictures (in chamber) for comparison, looking for cable inteferances.

Jeff, Sheila, Rahul

Details about OPO health check issues (Yaw dof. - frequencies are off and unnecessary peak observed) is currently being analyzed - see Jeff's alog 88913.

This morning we discussed about possible cable interferences in OPO.

I went into the chamber and took fresh pictures of the OPO from several angles, focusing on cable routing, cable resting on the OPO etc - please find them attached below. I will compare them with the pictures posted in LHO alog 61643 (by Sheila in 2022) and look for possible culprits (a few of them already).

Moving cables could cause some misalignment, hence we will start doing so once Sheila gives us a green light.  

Images attached to this report
Comments related to this report
rahul.kumar@LIGO.ORG - 15:11, Tuesday 27 January 2026 (88920)

This afternoon Sheila and I went into the chamber and nudged some of the cables away from the OPO - Jeff will re-check the TF measurements to look for any improvements. 

There is a cable connector sitting on the OPO (which is a new addition to the OPO). I lifted that cable connector and then Sheila looked for alignment shifts - which she confirmed. For now we left the cable connector at the same spot on the OPO. We will think of moving it away after Jeff's results.

Sheila also found some changes in the beam alignment since last week - not sure if this is due to our work (AOSEM re-centered LHO alog 88910) from yesterday - although centering aosem-flag should not change the mechanical alignment. 

corey.gray@LIGO.ORG - 08:37, Wednesday 28 January 2026 (88938)EPO

EPO tagged

X1 DTS
joshua.freed@LIGO.ORG - posted 16:49, Sunday 25 January 2026 - last comment - 11:15, Wednesday 28 January 2026(88873)
SPI Pathfinder, Comprehensive Phase Noise measurements

J. Freed,

Continuing From 88293, I took phase noise measurements of waveform generators relevant to SPI pathfinder with two different methods. This first method is the standard method that LIGO uses which follows the BluePhase 1000 manual. I used this method to highlight the issues this method has in the context of SPI. The second method is a slight modification to the standard method which shows a lower noise floor in the area of interest for SPI.


First Method:  BluePhase1000_Setup.png (from LIGO-T2400324) Shows a simplified Phase noise measurements set up of what the BluePhase 1000 manual provides. A simple way to take phase noise measurements is to mix the signal from the Device under Test (DUT) with a reference device (REF) outputting the same frequency but at quadrature. Ideally, this mix outputs only the differential noise between the two devices. If the reference device has much better performance, then the mix ideally outputs only the DUT noise. In this method, a feedback loop is used to keep the REF at quadrature with the DUT. For the REF device, I used the 80MHz OCXO housed in LIGO-D1100663

OCXOComparisonTOCXO.png Shows the results from the first method, I used 3 different devices as the DUT; a 80MHz OCXO here at LIGO LIGO-S1000565, a SRS SG382, and a Keysight 33600A. The main thing of note is that OCXO is expected to have a much lower noise floor than any other device; however, below ~60Hz the noise is not limited by the different DUTs. Since the REF is another OCXO, I believe the feedback loop that keeps the REF device in quadrature is limiting measurements below 60Hz.  Since SPI is interested in phase measurements well below 60 Hz this first method will not work for taking phase noise measurements for SPI. Especially since SPI has both an 80Mhz and an 80MHz -4096Hz signal and LIGO  does not have a 80MHz -4096Hz OCXO to use as a ref. 


Second Method: PhaseNoiseSetUp.png shows the modified set up; where the REF device is the SRS SG382. This method puts the REF device at quadrature by setting it manually and holding it there through the 10MHz timing port created by dividing by 8 the 80MHz OCXO signal. Since both the REF and DUT are referenced to the same OCXO (or the DUT is the OCXO itself), ideally both devices will be held at quadrature bypassing the need for a feedback loop. In practice, I did notice a small amount of drift from quadrature over time. 

OCXOComparisonSRS.png Shows the results from this method. This graph shows both the OCXO and the Double Mixer have phase noise performances well below the noise performance of a typical waveform generator (Keysight) below 100Hz. Though combined with the last alog, still very much better than SPI requirments.


Difference: OCXOComparisonSRSOC.png (ignore the title on this plot) shows the mix of an 80MHz OCXO and the SRS using the two different methods to hold one at quadrature with the other. With the modified method, we are not limited as much below 60Hz, except those peaks at ~0.16Hz, ~0.45Hz, etc.. which I believe are caused by the divide-by-8, not the SRS; as the SRS measurement using the first method did not have these peaks. 


Extra:

OCXOComparisonFull.png Shows all measurements on one graph.

OCXOComparisonKey.png Shows that Keysight had strange harmonics at multiples of 5kHz but disappeared 12 hours later. 

Images attached to this report
Comments related to this report
joshua.freed@LIGO.ORG - 11:15, Wednesday 28 January 2026 (88944)

Applying the equation found in 88293 to the data in the modified method, we get a new plot Keyrad3.png that shows the SPI noise budget for phase noise of oscillators used in the build/install of SPI. We can come to the same conclusion as last time, that since SPI has a reference interferometer the noise drops significantly at low frequency (the area where SPI operates). The noise from SPI's selected oscillators for the build/install is expected to have a negligible effect on our noise budget.

Images attached to this comment
H1 ISC (INS, ISC)
keita.kawabe@LIGO.ORG - posted 10:42, Saturday 24 January 2026 - last comment - 08:35, Wednesday 28 January 2026(88884)
JAC EOM update Friday Jan/23 (MattT, Mitch, Keita)

10-32x0.375" SHCS that was blocking the access to one 1/4-20 screw was replaced with a low profile 10-32 SHCS.

"Issue 2" in alog 88862 was solved.

See picture, Mitch found a 10-32x0.5" SHCS with a low profile head. 0.5" seemed to be OK in that it's not too long, but we used two washers to make sure that the scrwe doesn't bottom out.

Images attached to this report
Comments related to this report
keita.kawabe@LIGO.ORG - 14:16, Saturday 24 January 2026 (88886)

EOM crystal mounting practice part 2 (with a remote help from Michael)

Summary:

  1. "Laxen method" (no gap between the front plate and the input side, big gap for the output side) was repeated again with an extra caution (see below), no visible gap between the alumina piece and the electrode (with a help of flashlight), alumina doesn't slip out.
  2.  "Appert method" (even gaps for the input and the output) was tried twice, no visible gap between the alumina piece and the electrode, alumina doesn't slip out. 
    1. During Appert method tests we have found that the output side plate might be slightly warped.
  3. RF return dips were measured for all three of the above (one Laxen and two Appert mounting method), they were consistent regardless of the mounting method and were consistently higher than nominal with the alumina. (No RTP yet). It goes progressively worse as the frequency goes up. Michael told "The resonant dip needs to sweep across the desired frequency."
    1. Lower two frequencies (9.1MHz and 24.08MHz) look reasonable in that the nominal frequency is inside the observed dip.
    2. 45.5MHz dip is just barely on the shallow part of the dip curve.
    3. 118MHz is the worst, the nominal frequency is totally out of the dip (1MHz off).
  4. Michael suggested that the capacitance for the elctrorode-crystal is too small but we (Matt and I) couldn't see any light coming through the supposed gap.
  5. Michael also suggested that the windings of the inductor coils might have been bent (got looser) during shipment.
    1. I tested bending the coil windings for 118Mhz inductor so they come closer together and it had a huge impact. I was able to easily come close to a reasonable frequency, but it's no good unless we know that the capacitance for the crystal-electrode is OK.  I haven't changed trim cap nor touched any other frequencies.
  6. I'll measure the peaks without the alumina on Monday. Will discuss further with Michael, Stephen and Gabriele (while Masayuki is traveling to here).

Laxen method test.

In alog 88862 we left the EOM module with the alumina piece mounted using Laxen method (no gap between the input side plate and the front plate, a big gap for the output side).

Shining flashlight into the iput or output aperture in the side plates is useful to see the gap between the electrode plate and the alumina piece, and we found that there was indeed a small gap only on one side (i.e. the "crystal" was pinched at the edge).

I loosened the screws for the face plate and repeated the mounting procedure, but this time being extra careful to tighten the screws by tinier amount (than my previous attempts) at a time while applying a gentle pressure from the top. As soon as I got much tighter than finger-tight, I stopped. This resulted in what was seemingly a good contact between the alumina and the electrode, no light visible between them.

See  nogap.jpg, this is a representative picture of GOOD contact (even though I cannot prove that the contact is really plane-to-plane not just plane-to-one edge of the crystal).

Another picture gap.jpg is an example of BAD contact. It's hard to see but there's no gap at either edges closer to input/output faces, the gap is only in the middle. I don't have a good explanation for this.

Appert method tests.

We also tested Stephen's suggestion to make a gap on both sides of the front plate. This was trickier but doable by using two Allen keys. The third attachment (EOMassembly.jpg) shows the EOM placed on top of the EOM mount parts just for picture AFTER the alumina was mounted. During the mounting process, the face plate is facing down, and two allen keys will tighten two screws with green (or red) arrows in the picture with tiniest rotation at a time. Green, red, green, red, repeat it until it feels reasonably tight but much, much looser than you'll usually do for tight mechanical connection. After this was done, neither Matt nor I were able to undo the screws by finger.

We did this twice, both times no gap between the alumina and the board, and alumina didn't slip out.

Output side plate might be warped?

In the assembly picture, can you see that the gap between the face plate and the output side panel (right on the picture) is uneven, but the gap for the input (left on the picture) is fairly even? I don't think this is an optical illusion. This might be related to the reason why the crystal ALWAYS slips out when the face plate is tightened down to the output side plate, see my alog (88862). Quoting myself, "no matter what we did, the alumina piece (i.e. fake RTP for excercize) slid out of the assembly but only after tightening the screws". Maybe it's the output side plate.

Reflection measurement.

For each of the above three practices (one with Laxen method, two with Appert method), S11 coefficient was measured for all four ports.

What we found was that all four reflection dips were higher than they are supposed to be. According to Michael, alumina should give us similar results to RTP. I don't list results for all three sets (3x4=12 numbers) because numbers were pretty consistent across the sets, maybe give or take 10kHz or so. 

Nominal LHO/LLO (MHz) 9.100230 / 9.099055 24.078360 / 24.078 45.50115 / 45.495275 118.30299/118.287715
Measured (representative number) (MHz) ~9.17 ~24.10 ~46.05 ~119.8

In the attached pictures, green line is roughly where the center should be. 9.1 and 24.08 look reasonable to me. Not sure about 45.5MHz, it's 450kHz off. 118.3MHz is totally, totally off.

As I wrote in the summary, I tried bending the coil windings for the 118MHz (bendandsqueeze.jpg) because it was the worst but also because it was the one with the loosest of all four coils (118MHzWinding.jpg), and it had a huge effect. With just a few rounds of bending/squeezing I was able to go down to 118.53MHz (afterbending_118MHz.jpg). I could have passed 118.3 and gone to the other side easily but I stopped there.

Images attached to this comment
keita.kawabe@LIGO.ORG - 14:10, Saturday 24 January 2026 (88887)

Just in case somebody else must do this, here's what I did to measure S11 (reflection coefficient). 

If you go to the optics lab, everything is already set up like in the attached cartoon except that the dirty cable is removed from the coupler and placed on top of the optics table. You might still do the calibration again (because we turned off the analyzer at the end of the day and I cannot remember if the calibration results are kept in the analyzer). Remember that EOM is class A but your cables are dirty (even though we wiped the connectors of the dirty cable using q-tips and IPA). We're using one sacrificial SMA elbow that used to be class A to connect your dirty cable to the EOM.

Anyway, calibration. Set the frequency range to whatever you want but make sure that it covers the frequency range of main interest, like at least 9MHz to 125MHz or so while performing S11 calibration.

Connect the BNC of the dirty cable to the INPUT connector of the directional coupler, like in the attached cartoon.

Press "cal" button and select S11 calibration. Don't connect anything to the SMA of the dirty cable and press "Open" button. Next attach a hand-made short circuit plug to the dirty cable  via BNC male to SMA female connector. Press "Short". Then connect a 50Ohm SMA terminator to the dirty cable via SMA barrel. Press "Load". Then press "Done".

Now you're done with calibration. Press "Measure" and make sure that you're measuring S11.

Clean the SMA with IPA and q-tip again. Connect the dirty cable to the elbow, and the elbow to the EOM. Set the frequency range to whatever you want. That's it.

Images attached to this comment
keita.kawabe@LIGO.ORG - 16:25, Monday 26 January 2026 (88892)

Quick Monday update.

I  measured S11 coeff without the crystal/alumina but with the front panel.

Reflection dips with/without alumina are:

~9.17/9.192 ~24.10/24.214 ~46.05/47.106 ~118.53/122.736

So the frequencies are consistently higher without the crystal/alumina.

corey.gray@LIGO.ORG - 08:35, Wednesday 28 January 2026 (88937)EPO

EPO tagged

LHO VE
jordan.vanosky@LIGO.ORG - posted 16:33, Friday 23 January 2026 - last comment - 08:33, Wednesday 28 January 2026(88876)
Removal of the Relay Tube Viewport Assembly

In prep for HAM7 closeout, the temporary viewport assembly was removed from the HAM5 relay tube port. RV-1 was closed, and the volume vented with viewport covers still installed, with dry N2. I monitored the corner pressure (PT-120B) during venting, to make sure there were no leaks through the gate valve. No change in pressure, so I continued with viewport removal.

Viewport was removed first, then the pump-out tee. The mitered spool piece and bellows assembly was installed on HAM5 side. Lines were marked across the relay tube assembly prior to removal, so the install orientation remained the same. 

The ported spool piece will be installed next week during Laser Safe conditions. Bellows flanges were covered with foil for protection.

Images attached to this report
Comments related to this report
corey.gray@LIGO.ORG - 08:33, Wednesday 28 January 2026 (88936)EPO

EPO Tagged.

H1 SQZ (SQZ)
karmeng.kwan@LIGO.ORG - posted 16:33, Thursday 22 January 2026 - last comment - 08:30, Wednesday 28 January 2026(88859)
HAM7 and SQZT7 iris photos

[Sheila, Karmeng]

We took a bunch of photos on HAM7 and SQZT7 today, the IR-green coalignment is fixed. 

IR-green coalignment: on the iris between ZM3 and FC1 (before and after) and after AM3 (green and red overlap)

Beam position for all 3 irises placed in HAM7:

Iris 1 IR position on the iris placed between ZM1 and ZM2.

Iris 2 IR+green position on the iris placed between ZM3 and FC1.

Iris 3 IR position on the iris placed between BM4 and ZM4, with "RL" on the Thorlabs IR card placed on the iris as a reference to estimate the deviation from the center of the iris.

For 2 irises placed on SQZT7 HD path:

Iris 1 IR position on iris1 on SQZT7.

Iris 2 IR position on iris2 on SQZT7.

We also checked the IR on HAM7 QPDs path, the IR is off centered on the lens (seen from both front and back). This was roughly centered, and will be fine tuned with the picos.

Images attached to this report
Comments related to this report
corey.gray@LIGO.ORG - 08:30, Wednesday 28 January 2026 (88935)EPO

EPO tagged.

H1 IOO (IOO)
rahul.kumar@LIGO.ORG - posted 13:04, Wednesday 21 January 2026 - last comment - 09:41, Wednesday 28 January 2026(88834)
HAM1 update - JAC damper

Jason. JennieW, Rahul

This morning we added the damper parts to the JAC in HAM1 chamber - see picture attached. The cables were re-routed slightly so that they don't interfere with the damper.

I have finger tightened the screws of the damper for now - since no torque spec was provided and we were worried that tightening them too much might affect its position/angle.

Images attached to this report
Comments related to this report
corey.gray@LIGO.ORG - 08:27, Wednesday 28 January 2026 (88934)EPO

EPO-tagged.

jason.oberling@LIGO.ORG - 09:41, Wednesday 28 January 2026 (88941)

Masayuki and I fully tightened the JAC body mode dampers yesterday.  We were only able to get the screws ~1/2 turn past finger-tight before we could no longer tighten them.  No changes in JAC alignment were observed while we were doing this.

H1 SUS (SUS)
ryan.crouch@LIGO.ORG - posted 11:44, Wednesday 21 January 2026 - last comment - 08:25, Wednesday 28 January 2026(88828)
2nd HXDS received from LLO

Yesterday I picked up the shipment from LLO contain the 2nd HXDS (first HXDS shipment alog87998) and related ASSEYs and brought it to the Triples lab. 

Uwrapping and inspecting was uneventful, the zip ties were intact, the shock pads untripped and the humidity indicator was unchanged in color. The outer (front, back) and inner (front, back) bags were in good condition, unwrapping the suspension I found no play with the blades.  All the nuts and dowel pins were tight and well seated, the ICS looks good except for it seems to be missing the HDS Intermediate Mass Fixture (D2000230-V1, s/n 08). The part is scribed as V1, on the dcc there's a V2 with two added 8-32 helicoils taps that, based on D1900352 which uses V2, I should be able to see from the front and I don't, so this is a V1 plate and not an incorrectly scribed V2. I believe these two missing 8-32 holes are where we will attach the BOSEM Mounting plate (D2000257). The first HXDS we received in November had the V2 plate. We may have to do a small rework to update it to V2, or have LLO send the V2 part if possible.

Images attached to this report
Comments related to this report
corey.gray@LIGO.ORG - 08:25, Wednesday 28 January 2026 (88933)EPO

EPO tagging

Displaying reports 1-20 of 86410.Go to page 1 2 3 4 5 6 7 8 9 10 End