Displaying reports 21-40 of 86133.Go to page 1 2 3 4 5 6 7 8 9 10 End
Reports until 17:11, Monday 22 December 2025
H1 IOO
jennifer.wright@LIGO.ORG - posted 17:11, Monday 22 December 2025 (88644)
Tried Swapping in old POP X WFS

Last week Phil gave me the old POP X IN-AIR WFS PD as our JAC WFS A PD had a wobbly pin on the Q3 LO output.

Masayuki had tried connecting to this with both cables we had.

When I tried plugging in the Q3/Q2 cable on the POP X WFS I realised that one of these cables itself will not seat on this connector properly. I tried with the other cable and this one connects to the Q3/Q2 output on POP X ok.

I will get together with Phil in the new year and investigate more.

H1 ISC
jennifer.wright@LIGO.ORG - posted 17:01, Monday 22 December 2025 (88643)
Covered up stuff with foil in HAM1

Jennie W, TJ, Ryan C

 

Went into HAM1 and covered up everything that wasn't already covered (a single screw on the left-hand HEPI pier and some iris parts on the table).

Ryan C put extra clips on the C3 cover.

HAM1 should be all cosy for the holiday.

LHO General
ryan.short@LIGO.ORG - posted 17:01, Monday 22 December 2025 (88642)
Ops Day Shift Summary

TITLE: 12/23 Day Shift: 1530-0030 UTC (0730-1630 PST), all times posted in UTC
STATE of H1: Planned Engineering
INCOMING OPERATOR: None
SHIFT SUMMARY: Light day of work today. SQZ beam alignment continued in HAM7 (alog88641), the EY wind fence was patched up (alog88640), more clamps were placed on HAM1 door covers for the break, and fire pumps were churned. HAM7 alignment will continue and hopefully conclude tomorrow, then the LVEA will be transitioned to Laser SAFE.
LOG:

Start Time System Name Location Lazer_Haz Task Time End
15:57 SAF LASER LVEA YES LVEA is LASER HAZARD (\u2310\u25a0_\u25a0) 10:51
16:08 FAC Kim, Nellie LVEA - Technical cleaning 17:59
16:54 FAC Eric Site N Running fire pumps 17:35
17:36 SEI Jim, Randy, Mitchell EY N Wind fence work 20:04
17:54 CDS Erik FCES N Fix Wifi 18:10
19:46 FAC Kim EX N Technical cleaning 20:23
20:47 SQZ Sheila LVEA YES HAM7 SQZ beam alignment 23:57
20:47 CDS Dave MER, EY, MY N Setting up signage 21:32
21:13 AOS RyanC LVEA - Adding clamps to HAM doors 21:48
21:42 SQZ Kar Meng LVEA YES HAM7 SQZ beam alignment 23:57
22:46 AOS Richard LVEA - Checking in at HAM7 23:00
00:05 JAC Jennie LVEA, Prep Lab - Parts checks 00:30
00:52 OPS TJ LVEA - Checks and walkthrough 01:00
H1 AOS
sheila.dwyer@LIGO.ORG - posted 15:53, Monday 22 December 2025 (88641)
HAM7 alignment progress

Kar Meng, Sheila

I walked FC1 back to it's original slider position 88602 while walking the two steering mirrors between the OPO and SFI1 to keep the beam transmitted towards ZM4. Once this was done the beam was hitting the beam dump meant to catch the reflection off the beam diverter from the IFO.  I touched the last mirror on the VIP, B:M4, to bring the beam towards the center on the iris in front of ZM4, and then Kar Meng was able to see a beam on the SQZT7 periscope.  

Before we started: ZM4: P -338.7 Y -1297.7 ZM5: -120 P -460 Yaw  We moved ZM4 +5 to get the transmitted beam onto the OPO IR PD, ZM4 -338 P -1297.7 Y, ZM5 -720 P 839 Y.  Then we were able to align the CLF to the cavity a bit better by watching the flashes on the scope.  We can see evidence of clipping as the ZMs drift in the purge air the transmitted power fluctuates,  

We adjusted the in chamber CLF refl steering mirror to center on the CLF top periscope mirror, and Kar Meng aligned the CLF refl shutter PD using mirrors on SQZT7.  We were able to see that the OPO was semi-locked on the dither lock, but this wasn't stable. 

H1 SEI
jim.warner@LIGO.ORG - posted 11:54, Monday 22 December 2025 (88640)
Wind fence patched for the end of the year

Last week we found that some of the hardware on the EY wind fence had broken, which meant some of the main support wires for the fence were dangling free, weakening the fence and possibly further damaging the scrim in any future storms. The main failures were in the all thread that goes through the posts and attach the wire anchor points to the post. We had a limited window today to go and try to patch the fence this morning, so that's what Randy, Mitch and I did. Forecast promised us some sun, but that never really materialized, so it was pretty chilly. Fence is patched up now, Randy and Mitch will return the lift to LEXC this afternoon, after everybody thaws out. 

Images attached to this report
H1 PSL
ryan.short@LIGO.ORG - posted 11:48, Monday 22 December 2025 (88639)
PSL 10-Day (+7) Trends

FAMIS 31117

Since I missed pulling these trends last week, I plotted a total of 17 days this time around. Overall, things look to be running smoothly. Robert was in the enclosure 6 days ago tracing cables, which shows clearly in the relevant trends. The PMC and RefCav have needed some alignment touchup since the power outage based on the beam images, so I'll do that either today or tomorrow before the holiday break.

Images attached to this report
LHO VE
david.barker@LIGO.ORG - posted 10:19, Monday 22 December 2025 (88638)
Mon CP1 Fill

Mon Dec 22 10:05:09 2025 INFO: Fill completed in 5min 5secs

 

Images attached to this report
H1 CDS
david.barker@LIGO.ORG - posted 09:55, Monday 22 December 2025 (88637)
Mechanical Room Zeks Dryer Skid Cameras Linked on CDS web page

I have added a link to the Vacuum section of the CDS web page which opens the latest Zeks dryer skid camera images. These images are running on the virtual FOM cdsws12, display=5. They are updated every minute.

Gerardo has placed a clock on top of the skid to give a timestamp.

link to image is:

cdsws12_5-1.png

 

Images attached to this report
H1 CDS
david.barker@LIGO.ORG - posted 09:08, Monday 22 December 2025 (88636)
fire pump alarms bypassed for churn testing

Bypass will expire:
Mon Dec 22 01:07:27 PM PST 2025
For channel(s):
    H0:FMC-CS_FIRE_PUMP_1
    H0:FMC-CS_FIRE_PUMP_2
 

H1 PSL
ryan.crouch@LIGO.ORG - posted 08:55, Monday 22 December 2025 (88635)
PSL Status Report Weekly FAMIS 27623

Closes FAMIS27623, last checked in alog88538


Laser Status:
    NPRO output power is 1.839W
    AMP1 output power is 70.55W
    AMP2 output power is 139.7W
    NPRO watchdog is GREEN
    AMP1 watchdog is GREEN
    AMP2 watchdog is GREEN
    PDWD watchdog is GREEN

PMC:
    It has been locked 12 days, 15 hr 38 minutes
    Reflected power = 25.34W
    Transmitted power = 105.7W
    PowerSum = 131.1W

FSS:
    It has been locked for 3 days 16 hr and 18 min
    TPD[V] = 0.5215V

ISS:
    The diffracted power is around 4.1%
    Last saturation event was 5 days 19 hours and 36 minutes ago


Possible Issues:
    PMC reflected power is high

LHO General
ryan.short@LIGO.ORG - posted 07:46, Monday 22 December 2025 (88634)
Ops Day Shift Start

TITLE: 12/22 Day Shift: 1530-0030 UTC (0730-1630 PST), all times posted in UTC
STATE of H1: Planned Engineering
OUTGOING OPERATOR: None
CURRENT ENVIRONMENT:
    SEI_ENV state: MAINTENANCE
    Wind: 6mph Gusts, 4mph 3min avg
    Primary useism: 0.02 μm/s
    Secondary useism: 0.23 μm/s 
QUICK SUMMARY: Cold and foggy morning on-site. Lighter days of work planned for the next couple of days, but at this point here's the outlook:

LHO VE
david.barker@LIGO.ORG - posted 10:23, Sunday 21 December 2025 (88633)
Sun CP1 Fill

Sun Dec 21 10:08:07 2025 INFO: Fill completed in 8min 3secs

 

Images attached to this report
LHO VE
david.barker@LIGO.ORG - posted 10:36, Saturday 20 December 2025 (88631)
Sat CP1 Fill

Sat Dec 20 10:07:39 2025 INFO: Fill completed in 7min 36secs

 

Images attached to this report
H1 CDS
david.barker@LIGO.ORG - posted 10:32, Saturday 20 December 2025 - last comment - 10:35, Saturday 20 December 2025(88629)
Camera install in Mechanical Room viewing Zeks Air Dryer

Gerardo, Richard, Erik, Dave:

Over the holiday break we need to remotely view the operation of the Zeks Eclipse air dryer skid in the mechanical room to ensure no moisture gets into the LVEA chambers.

I initially setup a fisheye camera (a repurposed gate-cam), which gave a good view of the panel's LEDs and the mechanical gauges, but lacked the resolution to view the LCD display screen to see the Dew Point signal.

I then installed an Axis 214PTZ camera, which was able to zoom into the LCD display and read the values.

So we are now running both cameras side-by-side. 

sw-mech-aux was configured to have both ports 13 and 14 on the VID-LAN (10.106.0/24).

I ran two 60-foot cat5e ethernet cables from the vacuum rack (where the switch is located), over to the front of the Zeks skid, using the overhead mezzanine railing to provide a temporary "cable tray". 

Camera name/ip ethernet connection
fish-eye (POE) wincam (10.106.0.243/24) long run to POE injector on top of vac rack, short run to switch port14
PZT cam mechcam (10.106.0.244) direct to switch port13

Because the Axis camera is AC powered, we ran an extension cable from the vac rack to the base of the skid, passing it under the stairs to prevent it being a trip hazard.

Images attached to this report
Comments related to this report
david.barker@LIGO.ORG - 10:35, Saturday 20 December 2025 (88630)

Next to do:

1) fish-eye cam does not seem to be streaming, I have to hit reload on my web browser to refresh the image.

2) start software to capture these images every minute and post them to the CDS web page

H1 CDS
david.barker@LIGO.ORG - posted 10:07, Saturday 20 December 2025 - last comment - 09:44, Sunday 21 December 2025(88627)
Frontend Network Switch Failure, 12:04 Friday 19th December 2025

Erik, Tony, TJ, Jonathan, Dave:

at 12:04 Fri 19dec2025 PST we had a MSR network switch failure which took down the network for all the front ends, the /opt/rtcds NFS server and Guardian.

The Brocade Ruckus Network Switch SW-MSR-H1FE-STK (1/3) was found to be powered off (no LEDs illuminated). This is a ICX7150-48-4X10GR-RMT3 48port unit with firmware version 08.0.95g.

This unit is being powered by a Geist power distribution box, which itself is UPS powered, so all power cords are ORANGE. A second switch is also being powered by the Geist, and both it and the Geist were powered up.

We disconnected the failed switch's power cord (as found it seemed to be well connected, not loose) and plugged it back in, the switch did not light up. We then ran a longer power cord to the main rack power strips, again the switch did not light up. We then returned to the original power cord from the Geist.

While we were scratching our heads planning the next move we noticed the switch was lit up. We think it took at least a few minutes to show signs of life after its power cord was inserted.

We then let it boot up, which took a suspiciously long time, we expected something like 5 minutes but it was actually close to 15 minutes. At that point the network was returned to all the systems attached to this switch.

At this point all the front ends had returned in their running state, except h1sush12 and h1asc0 which had persistent DAQ errors. We restarted these frontends.

Many Guardian nodes were disconnected from the frontends, so we elected to reboot h1guardian1. It came back up with no problems.

Currently we do not know why this switch powered down. If it happens again our options are:

1) power it directly from the UPS rack power strip (i.e. not from the Geist) and give it plenty of time to show it is powering up

2) replace it with a spare switch

Comments related to this report
david.barker@LIGO.ORG - 10:16, Saturday 20 December 2025 (88628)

We also do not know why h1sush12 and h1asc0 had DAQ errors when the power was restored. Of all the corner systems, they did have recent hardware changes. They also had model changes, but so did h1lsc0.

david.barker@LIGO.ORG - 09:44, Sunday 21 December 2025 (88632)

FRS36424 ticket opened for this issue.

H1 SQZ
eric.oelker@LIGO.ORG - posted 21:01, Friday 19 December 2025 (88626)
More alignment work in HAM 7

[Kar Meng, Sheila, Eric]

We spent some more time today getting HAM 7 squared away after the VOPO swap.  This morning, we plugged in the new oven stage controller and tested out the new translation stage and cabling.  Everything worked as expected.  After we were done testing, Sheila moved the new controller to the SQZ cabinet for storage.

This afternoon we continued work with recovering alignment on the 1064 path in transmission of the VOPO.  Yesterday, we managed to roughly align everything in the chamber except for the iris before ZM4.  However, we ended up walking FC1 a bit to get the retroreflected beam from the filter cavity back through SFI1.  Today we started to slowly step FC1 back to its original position recorded in (88602) while walking the two steering mirrors on the VIP between the VOPO output and SFI1 to compensate.  We managed to get back to our original pitch position and about halfway back to our original yaw value while still keeping the beam roughly aligned through all aperatures up to the edge of the VIP.  However, we found that the beam coming off the VIP was still not aligned properly through the Iris in front of ZM4.  In fact, it had moved further in the -Y direction and is now clipping on the black glass beam dump for the FC1 wedge.  We were a bit disappointed at this point to find that we weren't making progress recovering the original SQZ path alignment.  

We then decided to turn on the FC 532 field to see if the 532 and 1064 FC paths were reasonably well co-aligned.  We were hoping that the 532 field might provide us with an additional alignment reference since, in principle, it should still be properly co-aligned with the transmitted 1064 field from the old VOPO.  However, we discovered that the FC green field was not well aligned to the iris we'd placed after ZM3.  It was about a quarter inch too low on this iris. Also, along the beam path right after the VIP, the 1064 and 532 fields are off from one another in both the horizontal and vertical directions.  Unfortunately, we did not think to double check the 532/1064 co-alignment carefully when we were setting up the irises using the transmitted seed beam from the old VOPO, so we're unsure of exactly what happened here.  A few thoughts:

H1 General
ryan.crouch@LIGO.ORG - posted 16:34, Friday 19 December 2025 (88623)
OPS Friday Day shift summary

TITLE: 12/19 Day Shift: 1530-0030 UTC (0730-1630 PST), all times posted in UTC
STATE of H1: Planned Engineering
INCOMING OPERATOR: None
SHIFT SUMMARY: HAM7 work continued, JM TFs were taken, HAMs 3 & 4 and were locked, and a network switch went down around noon and took all the front ends with it. The PSL cameras were taken down for a measurement today and someone who knows how needs to bring them back up sometime.
LOG:                                                                                                    

Start Time System Name Location Lazer_Haz Task Time End
15:57 SAF LASER LVEA YES LVEA is LASER HAZARD (\u2310\u25a0_\u25a0) 10:51
15:35 EPO Corey Yarm N Take pictures 16:31
15:25 FAC Randy LVEA Y Craning 15:43
15:25 ISC Sheila LVEA Y Check on laptop 15:30
15:49 FAC Nellie, Kim LVEA Y Tech clean 17:10
16:29 EE Fil LVEA Y Start disconnecting IOT2L 17:42
16:49 ISC TJ LVEA Y Start moving IOT2L 17:42
16:59 FAC Randy LVEA Y Help TJ move table 17:37
17:05 PSL Alicia, Jean-Rene LVEA Y Turn off cameras near PSL enc 18:02
17:47 FAC Richard LVEA Y Walkthrough 18:08
17:55 FAC Nellie, Kim LVEA Y Tech clean 18:29
18:22 VAC Travis LVEA Y Turn down purge air for HAM1 for JM measurement 18:25
18:33 ISC Masayuki LVEA Y Drop off parts at HAM1 19:53
18:36 SEI Jim, Randy LVEA Y Lock HAM3 HEPI, then remove PEM ST endcaps 20:01
18:39 SQZ Sheila, Kar Meng, Daniel LVEA Y HAM7 checks, OPO, Kar Meng out at 23:36 00:00
18:58 OPS Tony LVEA Y Talk to jim about HAM1 shaking 19:09
20:02 CAL Tony PCAL lab Y PRep meas 20:12
20:36 VAC Travis LVEA Y Turn purge air back up 20:39
21:26 ISC Masayuki Optics lab LOCAL JAC ASSY work 22:08
21:55 ISC Jennie LVEA, Optics lab Y Look for, and gather JAC parts 22:13
21:35 FAC Richard, plus crew OSB roof N Look at the view 21:56
22:15 FIT Matt, Anna, TJ, Masayuki, Gabriele, ... Xarm, Yarm N Running 23:51
22:57 ISC Jennie LVEA HAM1 Y Put away JAC parts, cleanup for break 00:20
23:25 PEM Robert LVEA Y HAM7 23:43
23:40 OPS Tony LVEA Y Help Jennie at HAM1 00:20
00:05 ISC Masayuki LVEA Y Help Jennie 00:20
Displaying reports 21-40 of 86133.Go to page 1 2 3 4 5 6 7 8 9 10 End