Displaying reports 41-60 of 86528.Go to page 1 2 3 4 5 6 7 8 9 10 End
Reports until 14:13, Wednesday 04 February 2026
H1 SUS
oli.patane@LIGO.ORG - posted 14:13, Wednesday 04 February 2026 (89015)
OPO is good to go for HAM7

Jeff, Oli

We were a bit unsure yesterday about the OPO but after some more measurements today I've confirmed that it is looking good. It still doesn't look like it did in 2022, but it works for us.

After some cable redressing last week the OPO was looking a lot better (88921), and then some further redressing was done (88957), which didn't seem to help, but at least didn't make Yaw worse. Those measurements were all taken with the ISI Locked. Yesterday I took what were supposed to be closeout measurements with the ISI now unlocked and DAMPED, but those measurements looked different from last week's, and not in a good way. There were two sets of measurements taken yesterday, one with the OPO damping all off (2026-02-03 1815UTC), and one where the DOF being measured was turned off, but the other DOFs were left damping (aka semi-off) (2026-02-03 1730UTC). Both measurement sets looked about the same besides a small increase in the highest frequency peak, but nowhere near the height it had been at last week(regular, zoomed).

In both sets of measurements, the lowest- and highest-frequency peaks (cross-coupling from T and V, respectively) were much smaller than they had been last week (last week we had thought the lowest peak had been split off from the main Yaw peak, but it was actually a shifted T cross-coupling). This was unexpected. The only (known) difference between last week's measurements and these two sets is the difference in the ISI, Locked vs Unlocked and DAMPED.

We decided to look at previous OPO measurements(regular, zoomed, txt explaining timeline from Jeff) taken with the ISI Locked, DAMPED, and ISOLATED, and found that the OPO resonances go down in Q when going from Locked to DAMPED. It also looks like once the ISI is ISOLATED, the resonances will rise back up(better zoom in). This could make sense as to why we're only seeing changes in the T and V resonances since the ISI moving side to side or up and down while in DAMPING would couple more directly into the OPO than when the ISI rotates.

The only way to confirm this idea was to take more measurements while the ISI was either Locked again or ISOLATED. Since yesterday afternoon the ISI had to be Locked again, I was able to take some measurements this morning(2026-02-04 1545UTC(all damping off), 2026-02-04 1630UTC(damping semi-off)), and they confirmed that the OPO looks like it did last week(regular, zoomed). So we're pretty sure once the ISI is back to ISOLATED it'll look like it did when the ISI was Locked earlier today and last week.


Yesterday's Measurements
- ISI Unlocked and DAMPED
2026-02-03 1730UTC
- OPO M1 DAMP all ON EXCEPT for DOF we are measuring (Semi-Off)
Data
/ligo/svncommon/SusSVN/sus/trunk/OPOS/H1/OPO/SAGM1/Data/2026-02-03_1730_H1SUSOPO_M1_WhiteNoise_{L,T,V,R,P,Y}_0p02to50Hz.xml
r12868
Results
/ligo/svncommon/SusSVN/sus/trunk/OPOS/H1/OPO/SAGM1/Results/2026-02-03_1730_H1SUSOPO_M1_ALL_TFs.pdf
r12869

2026-02-03 1815UTC
- OPO M1 DAMP all OFF
Data
/ligo/svncommon/SusSVN/sus/trunk/OPOS/H1/OPO/SAGM1/Data/2026-02-03_1815_H1SUSOPO_M1_WhiteNoise_{L,T,V,R,P,Y}_0p02to50Hz.xml
r12868
Results
/ligo/svncommon/SusSVN/sus/trunk/OPOS/H1/OPO/SAGM1/Results/2026-02-03_1815_H1SUSOPO_M1_ALL_TFs.pdf
r12869

Today's Measurements
- ISI Locked
2026-02-04 1545UTC
- OPO M1 DAMP all OFF
Data
/ligo/svncommon/SusSVN/sus/trunk/OPOS/H1/OPO/SAGM1/Data/2026-02-04_1545_H1SUSOPO_M1_WhiteNoise_{L,T,V,R,P,Y}_0p02to50Hz.xml
r12874
Results
/ligo/svncommon/SusSVN/sus/trunk/OPOS/H1/OPO/SAGM1/Results/2026-02-04_1545_H1SUSOPO_M1_ALL_TFs.pdf
r12876

2026-02-04 1630UTC
- OPO M1 DAMP all ON EXCEPT for DOF we are measuring (Semi-Off)
Data
/ligo/svncommon/SusSVN/sus/trunk/OPOS/H1/OPO/SAGM1/Data/2026-02-04_1630_H1SUSOPO_M1_WhiteNoise_{L,T,V,R,P,Y}_0p02to50Hz.xml
r12878
Results
/ligo/svncommon/SusSVN/sus/trunk/OPOS/H1/OPO/SAGM1/Results/2026-02-04_1630_H1SUSOPO_M1_ALL_TFs.pdf
r12877


Comparison plots
2022 vs last week vs yesterday
/ligo/svncommon/SusSVN/sus/trunk/OPOS/Common/Data/alloposs_2026-02-03_H1SUSOPO_StillPossibleIssue_ALL_TFs.pdf
/ligo/svncommon/SusSVN/sus/trunk/OPOS/Common/Data/alloposs_2026-02-03_H1SUSOPO_StillPossibleIssue_ALL_ZOOMED_TFs.pdf
r12872

ISI Locked v Damped v Isolated
/ligo/svncommon/SusSVN/sus/trunk/OPOS/Common/Data/alloposs_2026-02-03_H1SUSOPO_MaybeMysterySolved_ALL_TFs.pdf
/ligo/svncommon/SusSVN/sus/trunk/OPOS/Common/Data/alloposs_2026-02-03_H1SUSOPO_MaybeMysterySolved_ALL_ZOOMED_TFs.pdf
r12871

Everything looking good today
/ligo/svncommon/SusSVN/sus/trunk/OPOS/Common/Data/alloposs_2026-02-03_H1SUSOPO_LookingGood_ALL_TFs.pdf
/ligo/svncommon/SusSVN/sus/trunk/OPOS/Common/Data/alloposs_2026-02-03_H1SUSOPO_LookingGood_ALL_ZOOMED_TFs.pdf
r12887

Images attached to this report
Non-image files attached to this report
LHO General
eric.otterman@LIGO.ORG - posted 14:10, Wednesday 04 February 2026 (89033)
AHU Fan 1 bearing replacement
The front fan bearing in Fan 1 inside AHU-1 was replaced this morning. Fan is currently off since Fan 2 is running in the lead position. 
H1 IOO (IOO)
masayuki.nakano@LIGO.ORG - posted 14:00, Wednesday 04 February 2026 (89032)
Quick JAC PZT calibration

All the whitening gain and filter are off.

at JAC-PZT_DRV_IN**/JAC-PZT_DRIVER_VOLTS: 532nm/179V = 2.97nm/V
at JAC-PZT_DRV_OUT_DQ = 532nm/8601cnts = 0.062nm/cnts

Images attached to this report
X1 SEI (INS, SEI)
jeffrey.kissel@LIGO.ORG - posted 13:36, Wednesday 04 February 2026 (89029)
SPi Optomechanics: Optical Fiber Feedthru, Path Cable, and Spool Assembly
J. Kissel
- D2500175 :: S3228003
   . D2100573
   . E2300345
- D2400281

I'm finally back in the optics lab, taking the next steps towards assembling the SPI. 

Specific to this entry -- I'm assembling the Class A clean components of the fiber-coupled seed laser light. In other words, I'm integrating 
    (1) S3228003*** -- One of the 4.5" (inch) 1064nm V-FT Optical Fiber Feedthrough (Feedthru) Conflat Flange (DIAMOND) (D2500175) -- which includes the "off the shelf" (OTS) feedthru and integrated 3 [m] patch cord (the industry jargon for fiber optic cable), and its MIT-designed strain relief assembly D2100573 -- all delivered to LHO after class-A cleaning and assembly at Caltech per E2400159.
    (2) the ANU-designed Fiber Storage Spool assembly, D2400281, of which we have two.

Sina characterized the power transmission of all three of the feedthrus at Stanford before the clean-n-bake process, and identified that S3228003 had 100% transmission, so I've chosen that to be assigned to the MEAS path, where we need the most input power (as it's distributed through the most number of beam splitters). I plan to further integrate the patch cord into the SuK fiber collimator S0272503 for no better reason that to "pair the S[...]03 feedthru with the S[...]03 fiber collimator." 

***The serial numbers for the OTS feedthrus (D2500175) are of the alpha-numeric form 2153228V00n, where n = 1, 2, 3. That full version of the serial number is indicated in their ICS record, but in order to conform to the mold of the DCC S-numbers, I truncated the format to be numeric, S322800n, i.e. removing the identical leading 215 and misleading/unnecessary V character in the middle. 

Pictured here is 
    - The pre-assembly components of the fiber storage spool (First) 
    - The completed assembly of the spool with S3228003's patch cord wound up within it (Second and Third)

The feedthru's patch cord still has a Thor Lab Narrow-Key Mating sleeve (but NOT polarization maintaining) ADAFCB3 that is not intended to be a part of the final assembly, just there for fiber storage during shipment. I'd yet to detach it in these pictures.

Commentary:
     - Coiling the fiber within the spool was nerve racking. It feels like you're trying to coerce dry spaghetti into a curve without it snapping. If you let it go, it "sproings" into a wild relatively straight mess. In the end, holding it all mid-air with both hands, I used the weight of the mating sleeve to slowly pull the coil tighter as I rotated the coil nudging the rest of the coil into the newer smaller circle, until I met the radius of the storage spool. I had the goal of coiling it with one end "on top" and the other "on the bottom" of the stack, but I gave up on that. Once to the desired radius and no smaller, I used the securing cross, resting loosely across only 1/4 of the spool to hold the bulk of the coil of fiber in place while I tucked the rest of the length into the guiding channel. This is doable with a chair and patience in the open space of the optics lab, but I'm not looking forward to ding this in chamber.
     - Thinking through the install, my current plan is as follows :: WHAM3 D5 is currently a 12 inch blank with no 4.5 inch flange adapters. So it *needs* to be replaced by a 12 inch to 3x 4.5 inch flange adapter. So let's create the full 12 inch flange assembly with the 2x, MEAS and REF, fiber feedthroughs and 1x 4.5 blank -- and spool the fibers -- in the optics lab. Then we bring and install the whole 12 inch assembly on to HAM3 as a whole. 
Images attached to this report
H1 SEI
jim.warner@LIGO.ORG - posted 11:25, Wednesday 04 February 2026 (89028)
HAM7 closeout tfs look like 2024 measurements, ok to put doors on

Took HAM7 close out measurements this morning. They look ok, like the measurements taken in 2024. I believe there are known OPO plant interactions with the ISI plant that make it difficult to get clean tfs like other chambers. We should be ok to close.

Images attached to this report
LHO VE
david.barker@LIGO.ORG - posted 10:41, Wednesday 04 February 2026 (89025)
Wed CP1 Fill

Wed Feb 04 10:07:32 2026 INFO: Fill completed in 7min 29secs

Gerardo confirmed a good fill curbside.

Images attached to this report
H1 General
oli.patane@LIGO.ORG - posted 07:33, Wednesday 04 February 2026 (89022)
Ops Day Shift Start

TITLE: 02/04 Day Shift: 1530-0030 UTC (0730-1630 PST), all times posted in UTC
STATE of H1: Planned Engineering
OUTGOING OPERATOR: None
CURRENT ENVIRONMENT:
    SEI_ENV state: MAINTENANCE
    Wind: 6mph Gusts, 5mph 3min avg
    Primary useism: 0.03 μm/s
    Secondary useism: 0.43 μm/s 
QUICK SUMMARY:

Work continues in chamber

Reminder that the LVEA is LASER SAFE EXCEPT around HAM1/2 and at height.

LHO VE (VE)
gerardo.moreno@LIGO.ORG - posted 18:09, Tuesday 03 February 2026 (89021)
FAMIS Task Completed for Corner Station Turbo Pump Stations

Functionality test for the corner station turbo pumps, see notes below:

Output mode cleaner tube turbo station;
Scroll pump hours: 7287.3
Turbo pump hours: 7309
Crash bearing life is at 100%

X beam manifold turbo station;
Scroll pump hours: 3389.9
Turbo pump hours: 3394
Crash bearing life is at 100%

Y beam manifold turbo station;
Scroll pump hours: 4160.3
Turbo pump hours: 2829
Crash bearing life is at 100%

FAMIS tasks 31332, 31340 and 31348.

H1 IOO (ISC)
jennifer.wright@LIGO.ORG - posted 17:36, Tuesday 03 February 2026 - last comment - 08:51, Wednesday 04 February 2026(89018)
JAC Mode-Matching and EOM Alignment

Jennie W, Masayuki N, Keita K, Betsy W

 

Today we worked on improving the mode matching of the HAM1 output beam to the IMC. We also noticed the beam was going through the EOM and clipping somewhere inside so had to move the EOM up and sideways by a small ampunt to fix this. We will need to redo the RF electrical testing and the modulation depth testing for the EOM.

 

We improved the mode-matching of the HAM 1 output beam to the IMC by moving the lens L2 further away from JM2. We did 3 moves of 1 inch each and regained the alignment into IMC each time by using JM3 and JM2 to regain the pointing. At the end of this process we had a mode-mis-match of 1.1 % into the IMC.

After this a clipping of the beam was spotted by Keita somewhere between JM2 and JM3. We traced this down to the beam clipping somewhere inside the EOM crystal. This was fixed by shimming up the EOM at three points, after this we checked the mode-mis-match and it was 0.7%.

Then we realised there was still some clipping in pitch and so moved the EOM towards the -Y side of the table slightly. After these moves the mode mismatch was still 0.63 %.

Then after some alignent checks Keita and Masayuki have realised we need to rotate the EOM relative to the beam. This will require a sawn-off allen key as one of the 3 bolts required to yaw the EOM on its base is too near the sma connector elbows.

Camilla informed me that the non-magnetic tools might have one clean sawn-off 1/4 " allen key so left these in a tote bagged up on the + Y side outside the clean room.

Comments related to this report
masayuki.nakano@LIGO.ORG - 08:51, Wednesday 04 February 2026 (89024)

- We put two of 91080A026 MCMASTER OR EQ (parts#37 for EOM assembly) under the baseplate to sim up the EOM.
- The IMC scan for the mode mismatch estimation is shown in the attached plot fraction of the HOM in IMC scan is as follows:

[After JAC_L1 adjustment]

fraction mean ± sem (nseg=13)
TEM00: 0.946604 ± 0.00119 (n=13)
TEM10: 0.010114 ± 0.000345 (n=13)
TEM2nd: 0.0185568 ± 0.000474 (n=13)
TEM01: 0.0247254 ± 0.000723 (n=13)
[L2_pos2_MCalign] finesse (=2π/FWHM) mean ± sem over TEM00 peaks: 524.733 ± 15.6 (n=26)

[After_EOM_moved] fraction mean ± sem (nseg=32)
TEM00: 0.866311 ± 0.00153 (n=32)
TEM10: 0.113113 ± 0.00144 (n=32)
TEM2nd: 0.00915663 ± 0.000228 (n=32)
TEM01: 0.011419 ± 0.000204 (n=32)
[After_EOM_moved] finesse (=2π/FWHM) mean ± sem over TEM00 peaks: 519.284 ± 12.3 (n=64)

Note: Since we have >10% first order mode for the last measurement, the mode mismatch would be lower than 0.9%.

Images attached to this comment
H1 SQZ
camilla.compton@LIGO.ORG - posted 17:01, Tuesday 03 February 2026 - last comment - 08:08, Wednesday 04 February 2026(89020)
FC QPD A Seg 3 seems to be broken inside enclosure

Randy, Sheila, Betsy, Kar Meng, Camilla

After Sheila and Kar Meng found an issue with FC QPD A segment 3 88991, and after discussion with Ali James, Sheila went into chamber to test it.

Started with flashlight to confirm A vs B. Then after unplugging QPDs at SQZ rack, Sheila removed the diode detector holder D2000384 from the enclosure D2000246 (marked part #4). Once the cables were plugged back in at the rack, the signals on segments 1, 2, and 4 fell to zero but the segment 3 signal stayed railed at +30. This shows the issue is most likely inside the sealed enclosure, which is not a trivial fix. We attempted to swap the in-vac cables on the diodes to be sure the issue isn't in the in-vac cables or feed-through the cable was hard to removed so we stopped. Finished with a flashlight test again.

After consulting Safety on the technique, we employed a plank on the stationary fork lift to add an extra seating-perch in order to reach and troubleshoot the issue.  Photo attached of Sheila "surfing". 

Images attached to this report
Comments related to this report
corey.gray@LIGO.ORG - 08:08, Wednesday 04 February 2026 (89023)EPO

Tagging for EPO

H1 General
oli.patane@LIGO.ORG - posted 16:40, Tuesday 03 February 2026 (89019)
Ops Day Shift End

TITLE: 02/04 Day Shift: 1530-0030 UTC (0730-1630 PST), all times posted in UTC
STATE of H1: Planned Engineering
INCOMING OPERATOR: None
SHIFT SUMMARY:  Lots of work towards finishing up in HAM1 and HAM7, including some surfing! LVEA is still LASER SAFE except behind the curtasins by HAM1/2 and at height.
LOG:                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                              

Start Time System Name Location Lazer_Haz Task Time End
22:49 SAF LVEA IS LASER SAFE LVEA NO* LVEA IS LASER SAFE *BIFURCATED HAM1/2 bring ur LASER GOGGLES 16:49
15:54 FAC Kim, Nellie LVEA Y/N Tech clean (Nellie out 17:04) 17:06
16:37 FAC Mitchell LVEA n Grabbing stuff 17:19
16:39 FAC Randy LVEA YES Craning near BSC2 20:30
16:55 PCAL Dripta, Tony EY YES PCAL measurements 19:56
17:00 FAC Chris, pest control LVEA Y/N Pest control 16:30
17:01 FAC Chris, pest control XARM, YARM n Pest control 18:31
17:03 FAC Nellie MY n Tech clean 17:10
17:06 VAC Gerardo LVEA Y/N Turning down purge air for HAM1 and HAM7 17:21
17:29 FAC Eric EX n Chiller yard work 18:07
17:41 SPI Jeff, Jim OptLab y(local) SPI work 21:03
17:54 FAC Kim EX n Tech clean 18:57
17:55 FAC Nellie MY n Tech clean 18:42
18:11 VAC Gerardo LVEA YES Turning up purge air 18:16
18:19 JAC Masayuki, Keita LVEA YES JAC mode-matching 20:07
18:31 JAC Jennie LVEA YES JAC work 20:07
18:31 JAC Jason, RyanS LVEA n JAC table 20:04
18:33 FAC Chris Mids, Ends n FAMIS tasks 20:22
18:41 VAC Gerardo LVEA n Turning HAM7 purge air up 18:51
19:04 SUS Rahul, Fil LVEA YES Troubleshooting PM1 19:11
19:24   Betsy OptLab, LVEA YES Cleaning up JAC stuff 20:30
19:39 FAC Kim LVEA n Putting away garb 20:13
19:41 VAC Gerardo LVEA n Turning on turbo pumps for FAMIS 20:41
20:46 PCAL Tony, Dripta EY YES PCAL measurements 01:32
21:01 SUS Rahul LVEA YES SUSing out PM1 23:05
21:06 FAC Randy LVEA YES Moving forklift to HAM7 and being the ocean that carries the surfboard 23:13
21:07   Jennie LVEA YES Helping move barriers for Randy 21:24
21:26   Betsy LVEA n Going out to help with surfing 23:42
21:27 SQZ Sheila LVEA n Surfing 23:56
21:28 JAC Keita, Jennie LVEA YES JAC work (jennie out 23:13) 15:08
21:35 JAC Jason, RyanS LVEA n JAC table work 01:37
21:35 SEI Jim LVEA n Locking HAM7 ISI 22:25
21:35   Camilla LVEA n Watching Sheila surf 00:19
21:59 JAC Masayuki LVEA YES JAC work 01:18
21:59 VAC Gerardo LVEA n Turning off turbo pumps 22:32
22:00 FAC Tyler LVEA n Talking to Betsy 22:14
22:33 FAC Chris MY n Snorkel lift work 23:05
22:33 SPI Jeff, Jim OpticsLab y(local) SPI work 23:48
22:34 FAC Chris LVEA n FAMIS tasks 21:49
22:58 BHD Elenna OpticsLab y(local) Putting away optics 23:14
23:21 JAC Jennie LVEA YES JAC work 01:37
23:27   KarMeng LVEA n Checking out HAM7 00:19
23:29   Travis LVEA n Grabbing parts 23:48
23:42   Betsy LVEA YES Helping with JAC 23:56
00:35   Camilla LVEA n Getting laptop 00:38
H1 SUS (SUS)
rahul.kumar@LIGO.ORG - posted 15:15, Tuesday 03 February 2026 - last comment - 13:49, Thursday 05 February 2026(89017)
HAM1: SUSPM1 investigation - OLC of all four BOSEMs dropped by 20%

Fil, Rahul

Out of chamber investigation

This morning Fil and I unplugged Tip Tilt PM1 cable going to its Satamp and connected it to Tip Tilt JM3 and found no change in its Bosem counts (was still low for UL and UR, like before). We connected JM3 to PM1's electronics chain and it was looking good. We also checked the long grey cable and found it to be healthy. Thus we came to this conclusion that in-air electronics chain is healthy for PM1.

In-chamber investigation

During lunch time when the chamber was empty, I took the OLC of all four BOSEMs for PM1 and found their values to be lower by 20% (last taken in April 2025).

Bosem OLC (April 2025) OLC (Feb 2026)
UL 264040 20800
LL 28894 23100
UR 24529 19100
LR 29276 23200

This tells me that either the in-vacuum cable is not working properly or all four Bosems are malfunctioning. I need more in-chamber time to further investigate this issue.

Comments related to this report
rahul.kumar@LIGO.ORG - 13:49, Thursday 05 February 2026 (89050)SUS

PM1 issue was due to coil drive swap in Dec 2025 - https://alog.ligo-wa.caltech.edu/aLOG/index.php?callRep=88998

Nothing wrong with the BOSEMs. cable or suspension. 

H1 TCS
ryan.crouch@LIGO.ORG - posted 12:04, Tuesday 03 February 2026 (88988)
TCS Chiller Water Level Top-Off - BiWeekly

Closes FAMIS27833, last checked in alog88799

  TCS X TCS Y
Previous Level 30.3 10.3
New Level 30.5 10.6
Water added mL 110 20

Values added to spreadsheet

H1 CDS
david.barker@LIGO.ORG - posted 11:26, Tuesday 03 February 2026 (89016)
TW1 raw minute trend offload started, nds1 needed a restart

WP13007 TW1 offload

Oli, Dave:

I started the offload process this morning. The first step is to freeze the past 6 months of raw minute trend data on TW1 and start writing current data to a new directory. While the copy is proceding, which takes 24 hours, NDS1 needs to serve the raw minutes from their temporary location. To this end, at 11:20 I reconfigured NDS1 daqdrc and restarted the rts-daqd.service. Oli recovered the control room FOM ndscopes after this restart.

H1 SQZ
sheila.dwyer@LIGO.ORG - posted 11:26, Monday 02 February 2026 - last comment - 13:28, Wednesday 04 February 2026(88991)
RLF QPD segment3

As noted on Friday, RLF QPD A segment 3 railed Nov 29th, and has been railed since then.  

Filiberto, Kar Meng, Marc and I went to the rack and swapped the two cables for WFS1 + WFS2 on D2000552.  The saturaed segment moved with the cable which could indicate the problem is the in vacuum QPD.  

The 105kHz segment went quiet at the same time as the problem on the DC segment.  This happened on a Saturday, before the chamber was vented.  It had been two days of not locking the squeezer or the IFO before this happened.  

Edited to add:  This is the QPD used for filter cavity length control.  We did lock the filter cavity after the segment broke, December 4th.  

Images attached to this report
Comments related to this report
sheila.dwyer@LIGO.ORG - 13:28, Wednesday 04 February 2026 (89026)

The attached plot show that the 105kHz channels from Q3 went quiet at the same time that the DC channel saturated, 10:40 pacific time Saturday Nov 29th.  Then, on Dec 3/4th, the squeezer and filter cavity were relocked, and the signal on the 105kHz channels for the other quadrants returned but not on the Q3 signals.  

This, along with the observation that the saturation didn't change when the QPD was removed (89020) , could point to the transimpedance amplifier being the problem, as that is common to the DC and 105kHz channels.  D2000341

Images attached to this comment
H1 SQZ
sheila.dwyer@LIGO.ORG - posted 17:58, Friday 30 January 2026 - last comment - 13:50, Wednesday 04 February 2026(88976)
HAM7 wrapping up laser work

Today Rahul and I worked on reducing the last bit of clipping in HAM7.  The power budget shows a couple of percent more loss than we've expected previously, but I don't think we can improve it much right now so this is good enough. QPDA segment 3 is railed. 

This morning we found that we had some loss on B:L2, see Rahul's power budget alog as of lunchtime: 88971.  In hindsight, this was also possible in the power budget that Kar Meng reported before the suspension work this week, 88847. We translated the beam in the -Y direction in the SFI2 aperture, so it would make sense that we might need to translate the lens in the -Y direction.  However, there is no space to move it because the mount is already as close as it can be to SFI2 (photo).  So, we translated the beam using B:M3, using the power meter to judge when we were improving the alignment.  We found that this aperture is very small, there isn't much of a plateau where we aren't clipping.  

After doing what we could to reduce the yaw clipping here we did a careful power budget with the thorlabs power meter, we seem to have  8% loss to SQZT7, 11-14% loss from output of the OPO to the homodyne, which is a bit worse than past measurements ( 65066): 

We attempted to move B:M3 in pitch to see if we could reduce clipping on B:L2 that way, but that did not improve the transmission.  In pitch we also saw that we increased the clipping with small moves in either direction.  I will try to look up the beam size and aperture size next week to see if this makes sense.  

We adjusted B:B4 and ZM4 a bit to align onto the two irises on SQZT7. 

We also walked the two picomirrors used to center the FC QPDs, with the seed beam which saturates the diode.  From the control room I reduced the power and was able to mostly center, but it seems that QPDA segment three has been railed at 33.9 since November 29th.  

After we finished up, I went back to check the FCGS alignment onto SQZT7, which was not good, so I went back in for a few minutes to get that beam onto the filter cavity reflection diode.  I also had a look at the red + green co-alignment, which looks similar to what Kar Meng posted in 88859.  

We also checked that the new cable routing doesn't block the beam onto H:PD1, we couldn't see the beam but we think it looks like a clear path.  Rahul also took a photo of where the beam exits SFI2. 

 

Images attached to this report
Comments related to this report
corey.gray@LIGO.ORG - 09:32, Tuesday 03 February 2026 (89009)EPO

EPO tagging.

karmeng.kwan@LIGO.ORG - 11:04, Tuesday 03 February 2026 (89014)

From the alog 59333, the waist (w) is 700um at 54mm away from BL2.

Beam diameter is 1.4mm on the BL2. The diameter of lens aperture is 0.2" (~5mm).

From the Gaussian beam equation, the ratio of of the clipping is given by e^[-2(R2/w2)]. For a beam centered in the iris, the loss is 0%.

sheila.dwyer@LIGO.ORG - 13:47, Wednesday 04 February 2026 (89030)

Here is a photo of BL2 taken from above.  We wondered if the lens mount being tilted could make the aperture smaller explaining losses, but it seems that this tilt is too small to explain a loss ~1%

Images attached to this comment
karmeng.kwan@LIGO.ORG - 13:50, Wednesday 04 February 2026 (89031)

From the calculation for clipping loss, I plotted the graph for clipping loss for the IR 700um waist versus lens aperture radius. This gives us rough estimate the loss.

Images attached to this comment
Displaying reports 41-60 of 86528.Go to page 1 2 3 4 5 6 7 8 9 10 End