Displaying reports 77501-77520 of 84690.Go to page Start 3872 3873 3874 3875 3876 3877 3878 3879 3880 End
Reports until 09:59, Tuesday 13 August 2013
H1 PSL
kiwamu.izumi@LIGO.ORG - posted 09:59, Tuesday 13 August 2013 (7422)
PSL switched to commissioning mode for 1 hour this morning

The PSL was switched to the commissioning mode this morning for approximately one hour for the weekly cleaning. Karen and I entered the PSL enclosure. After the cleaning the PSL was then switched back to the science mode again.

Note: when we followed Robert's instruction to switch it to the commissioning mode the HEPAs in the laser room didn't come up for some reason. We could notice it because the laser room was too quiet. This might be some sort of bug. Toggling the HEPAs off and on on the touch panel eventually made it running.

H1 IOO
jeffrey.kissel@LIGO.ORG - posted 07:45, Tuesday 13 August 2013 (7421)
Beginning IMC Crossover measurements
Beginning measurements of IMC Crossovers. 

Not sure why, but I found the IMC locked, but with the top (M1) stage turned OFF, gain sert to zero, with FMs 1 and 2 on. In order to engage M1, I
- turned off FM1 (the boost), turned on inputs and outputs
- used a TRAMP of 20, and ramped to a gain of 1.0 (probably didn't need to go that slow, but I didn't want to blow the lock)
- Turned on the boost filter.

Also found FM9 (CLP300) of M3 LOCK OFF, so I turned that ON.

The LOCK Gains are now [M1,M2,M3] = [+1,+0.2,-300].

Finally, all of the notch filters (FMs 6-10 in M3_ISCINF Bank) were OFF. Turning them on (both the R3 and V3 notches [FMs 6 & 7], the 1st, 2nd, and 3rd harmonic violin mode notches [FMs 8-10] independently) makes the loop unstable, as indicated by the MC2 output at all stages increasing wildly hitting the limiters. We'll have to explore / model that later.

Save the notches, and the factor of 2 difference in M2 and M3 gain, the configuration should be the same as what's at LLO.
H1 SUS
arnaud.pele@LIGO.ORG - posted 07:44, Tuesday 13 August 2013 - last comment - 10:51, Tuesday 13 August 2013(7415)
ETMX transfer function Phase 2c

Results of ETMX main and reaction chain top mass transfer functions for Phase 2c, after final alignement, are attached below. Most of the measurements are showing good agreement with the model, except for pitch, as on last thursday. The first two modes of the main chain @~0.55Hz and ~1.30Hz appears to be shifted down in frequency (page 5 of first pdf). The second pitch mode of the reaction chain @ ~ 1.33Hz is shifted up, and we can see vertical to pitch as well as transverse to pitch cross couplings from the extra 2Hz and 2.22Hz resonnances (page 5 of the second pdf). After plotting ETMX pitch transfer function against other fiber quads (3rd pdf), it seems like a common feature between quads. The results will be discussed during the sus meeting, but are approved for now since livingston ITMY looks identical.

Plots attached are described below :

1- H1 M0-M0 ETMX phase 2c main chain top mass transfer functions (in red) against "fiber" model (in blue), for the 6 degrees of freedom

2- H1 R0-R0 ETMX phase 2c reaction chain top mass transfer function (in red) against "erm (end reaction mass)" model (in blue), for the 6 degrees of freedom

3-a) Pitch to pitch main chain comparison between model and other fiber quads : L1 ITMX (June 2013, orange), L1 ITMY (Mai 2013, black), H2 ETMY (Mai 2013, pink), H1 ETMX (last week during alignement, cyan) and H1 ETMX (end of last week after alignement, green)

3-b) Pitch to pitch reaction chain comparison between erm model, H1 ETMX (most recent) and H1 ETMY (Mai 2013)

Non-image files attached to this report
Comments related to this report
arnaud.pele@LIGO.ORG - 10:51, Tuesday 13 August 2013 (7423)

After discution with sus commissioners, the main chain pitch mode is sensitive to d-effective values (distance between center of mass and fiber flexure point). Since the flexure point can move slightly depending on the shape of the fiber, it seems acceptable to have a shift in frequency for pitch.

For the reaction chain, pitch is sensitive to the way cables are wired, and again, it can vary from quad to quad.

ETMX is then approved for phase 2c, and TMSX team can move on with installation

H1 IOO
kiwamu.izumi@LIGO.ORG - posted 20:27, Monday 12 August 2013 - last comment - 20:40, Monday 12 August 2013(7419)
IMC autolocker is up running

In response to Jeff.K's request I set up the IMC autolocker so that it can automatically lock itself. So far it seems locking without difficulties. The IMC autolocker had been intentionally disabled until this evening for allowing people to run some measurements on the SUS/HEPI/ISIs. Jeff.K is volunteering to remotely run some cross-over measurements which I haven't finished (alog 7369) as a part of the IMC characterization. So Jeff, it is all yours until everybody wakes up !

The autolocker script, which I copied from Chris's original one and temporarily named as rudimentary_autolocker.2013.Aug.12.edition, is running on h1guarian0. It resides in userapps/ioo/h1/scripts/imc which is the usual IMC scripts place.

Comments related to this report
kiwamu.izumi@LIGO.ORG - 20:40, Monday 12 August 2013 (7420)

I forgot to mention one thing: the MC2 suspension was found to be misaligned a lot, resulting in no interferometric signals. It seemed that it had been misaligned since the last Tueday night probably due to some suspension related measurements/activities. Arnaud burt-restored the MC2 to 19:00 of the Tuesday and this brought the MC2 back to a good alignment where we could lock the IMC.

LHO General
justin.bergman@LIGO.ORG - posted 16:03, Monday 12 August 2013 (7418)
ops

0800-1000 High dust counts (+3000PCF@.5um) in EY while Apollo works on equipment staging.

0900 Pablo working in H2 enclosure

0910 Karen will be opening LVEA exit doors during cleaning

930 Thomas aligning optical lever to check for B coupling on PR3

1430 Pablo working in H2 enclosure again. All the time. Every day.

1500 H1 enclosure and PSL environmental sensors go slightly wacky. Readings of -4F and 0% humidity in laser room and anteroom. Maggie and Daniel working on Beckoff system.

H1 SEI
hugh.radkins@LIGO.ORG - posted 15:44, Monday 12 August 2013 (7417)
WHAM6 SEI HEPI is now Unlocked and Floating
Nothing really sensitive on this platform at the moment but the system is floating; please be mindful of the blue crossbeams.  We'll do Optical Table positioning tomorrow if IAS is available.
LHO General
bubba.gateley@LIGO.ORG - posted 15:41, Monday 12 August 2013 (7416)
Apollo crew
Today we relocated the E-module and the newly assembled clean room skeleton, as well as other extraneous "stuff" @ end y to allow for vinyl flooring installation to proceed tomorrow. We also started removal of FFU's and lights from the clean room located at ham 4 which is approximately 50% complete. Machined some vacuum accessories for Cheryl V. 
H1 SEI
hugo.paris@LIGO.ORG - posted 10:52, Monday 12 August 2013 (7413)
HAM - IMC chambers controls turned back on

Transfer functions were runnning over the weekend on HAM2 and HAM3 ISIs (tilt decoupling frequency meausrement).

Measurements are complete. Isolation loops, and HEPI alignment offsets were turned back on.

H1 CDS
james.batch@LIGO.ORG - posted 10:04, Monday 12 August 2013 (7412)
Access to lhocds has been restored.
Found computer completely unresponsive, rebooted.  Had to manually mount /ligo file system.
H1 SEI
hugo.paris@LIGO.ORG - posted 09:43, Monday 12 August 2013 (7411)
HAM6-ISI - HEPI can be unlocked

The transfer functions measured recently on HAM6-ISI featured a discrepancy between what was seen by GS13-V2 (purple curve), and what GS13-v1 (cyan) and GS13-V3 (yellow) would see. 

Thinking GS13-V2 could be saturating, we tried taking a new set of measurements over the weekend, with lower actuation. Reducing the actuation did not change the shape of HAM6-ISI TF, as seen on the latest results.

The transfer function measured with the CPSs show a good match between the corners, and confirm the good functioning of the platform, themselves, and the actuators.
 
I extracted the GS13 responses out of the TF measured on HAM6-ISI over the weekend. GS13-V2 has its resonance pretty low (~15%, blue curve) compared to what we usually see (red curve). This is what caused the discrepancy we saw.
 
Nothing alarming though. The sensor works fine, even in the worse configuration (see spectra with ISI tilted).
 
Moreover, the symmetrization filters we apply into the readout chain are maid to account for mismatch in GS13 resonance frequency. I made a quick set of symmetrization filters. Once symmetrized the TF feature a good match between the corners (see HAM6-ISI Symmetrized TF).
 
HAM6-HEPI can be unlocked.
Images attached to this report
LHO VE
kyle.ryan@LIGO.ORG - posted 12:13, Sunday 11 August 2013 (7410)
Can't access lhocds remotely today to view VE overview screen
I am on site (briefly) to verify vacuum system is Ok - it is - leaving now (1215 hrs.)
H1 AOS
cheryl.vorvick@LIGO.ORG - posted 00:01, Saturday 10 August 2013 (7409)
TMSX cable clamp removed - cables threaded through the top mass
I removed the screws and washers from the peek clamp bracket.  Washers were not reachable, but I was able to push them to a place where they dropped into a temporary foil shield I installed under the top mass.

Keita and I then removed the peek clamp and bracket by lifting it from the bottom and hooking it from the top with a dental pick.

Cable connectors were threaded from the top down, past the blade spring on the -Y side, with the orientation defined in D0901880-v5, while cables were held out of the way on the other side of the "H" slot in D1200469-v1.

Pictures:

P1030993 - peek clamp and bracket
P1030995 - bracket screw removed - loose washer remains
P1030997 - fishing for the peek bracket
P1030999 - bracket caught
P1050005 - "H" slot as seen from below before threading cables
P1050006 - "H" slot as seen from above before threading cables
P1050009 - "H" slot as seen from below after threading cables
P1050011 - "H" slot as seen from below after threading cables
P1050020 - cable connector seen from the side, as it just fits through 
                      the "H" slot around the blade spring (-Y side, left in this picture)
Images attached to this report
H1 ISC
alexan.staley@LIGO.ORG - posted 17:52, Friday 09 August 2013 (7408)
More on Noise Budgeting

(Alexa, Kiwamu)

 

I have attached the following graphs:

 

1) The most recent noise budget produced by the ALS HIFOY model

2) Plot of all the contributing sensor noise to the IR noise before applying the CARM control  (which is why we do not see a knee at high frequency when comparing to the noise budget graph)

3) Infrared Noise assuming:

S_IR  = S_sensornoise                                      for f < UGF of CARM feedback

S_IR = UGF/f * S_sensornoise                          for f>UGF of CARM feedback

Thus, we are assuming a 1/f behavior above the UGF, which should overestimate the RMS. This graph includes the current acoustic noise and that with the acoustic noise lowered by a factor of 10 predicted by Robert for the science run.

4) Plot of RMS vs UGF of CARM feedback. This graph indicates if the acousitc noise is lowered by a factor of 10 the UGF of the CARM feedback can be increased while reaminig under the noise limit of 8Hz.

Non-image files attached to this report
H1 SUS
arnaud.pele@LIGO.ORG - posted 16:58, Friday 09 August 2013 (7407)
ETMX transfer functions

Starting a new round of transfer functions on ETMX over the week end. GPS starting time = 1060127914

LHO VE
kyle.ryan@LIGO.ORG - posted 16:28, Friday 09 August 2013 (7405)
Manual CP1 level control passed to CDS PID @ 1230 hrs. local
Kyle 

Had valved-out inst. air to LLCV this morning while manually filling CP1 -> Hand over to PID control re-exposed known quirk with CP1's pneumatic actuator control box, that being a gas-column oscillation -> I adjusted (cw) the damping jet until the oscillations stopped -> Control behavior may be different as a result 

I will monitor from home
H1 General
andres.ramirez@LIGO.ORG - posted 16:00, Friday 09 August 2013 (7404)
Ops shift Summary
Work at LVEA – Richard

375 ml of distilled water added to the crystal chiller – Justin

Testing ITMx ( Spectra Test ) - Arnaud
H1 SEI
hugh.radkins@LIGO.ORG - posted 15:42, Friday 09 August 2013 (7403)
WBSC1 (ITMY) SEI HEPI Vertical L4-Cs swapped on Corners 2 & 4
We had tried some whack the Crossbeam repairs but this did not improve the response so we've exchanged:

                 C2      C4
Pulled  L41343  L41439
Install  L41451  L41333

from BSC1.
LHO VE
richard.mccarthy@LIGO.ORG - posted 09:50, Friday 09 August 2013 - last comment - 15:19, Friday 09 August 2013(7396)
Vacuum Crate LY Fail
The VME crate for the LVEA Y arm vacuum controls failed last night.  From initial investigation it looks like the power supply died.  I have swapped out the crate with a different one and re-installed all of the cards and cables.  Cyrus assisted in getting it back up and running. See his report.
Comments related to this report
john.worden@LIGO.ORG - 09:53, Friday 09 August 2013 (7397)

Richard,

Can we get a time of the failure? That will give us a good number on the LN2 boiloff rate.

 

thanks

cyrus.reed@LIGO.ORG - 10:10, Friday 09 August 2013 (7398)
Taking advantage of the unplanned downtime, the boot parameters on this crate have been changed to boot from the new vxworks boot server, vxboot.  It booted successfully with no visible errors, so the boot server has passed another test assuming the crate continues to run with no errors.  We will start to reconfigure the remaining vacuum crates to boot from the server as time and circumstances allow.
david.barker@LIGO.ORG - 15:19, Friday 09 August 2013 (7402)

h0vely failed at 01:26 UTC Friday, 18:26 Thursday local time. I'm investigating why no emails were sent to cell phones.

The DAQ EDCU did not reconnect to this IOC, I restarted the DAQ at 11:59 this morning to force a reconnection.

LHO VE
kyle.ryan@LIGO.ORG - posted 09:03, Friday 09 August 2013 - last comment - 16:29, Friday 09 August 2013(7394)
CP1 level low after loss of CDS computer
Found CP1 level @ 23" WC = 55% full at 0830 -> Determined CP1 LLCV fully closed via removing inst. air and observing no stroke -> Begin manual filling of CP1
Comments related to this report
kyle.ryan@LIGO.ORG - 09:09, Friday 09 August 2013 (7395)
28" WC = 68% full @ 0910 
john.worden@LIGO.ORG - 16:29, Friday 09 August 2013 (7406)

Kyle reports that the boiloff rate overnight averaged ~2.8%/hour   --  40% in 14 hours.  

The liquid reservoir is not purely cylindrical so this will likely be a non linear rate.

Displaying reports 77501-77520 of 84690.Go to page Start 3872 3873 3874 3875 3876 3877 3878 3879 3880 End