Displaying reports 121-140 of 81651.Go to page Start 3 4 5 6 7 8 9 10 11 End
Reports until 10:05, Wednesday 16 April 2025
LHO VE
janos.csizmazia@LIGO.ORG - posted 10:05, Wednesday 16 April 2025 - last comment - 10:40, Thursday 17 April 2025(83951)
Intentional pressure spike at the X-manifold
Janos - 9:50, LVEA

The X-manifold is valved out from the main volume both sides, the main turbo is pumping on it.
On the X-manifold I slightly opened up the suspicious blanked-off small Varian gate valve (see photo), to find out if it is opened or closed.
I moved very slowly the hand-actuator, and the pressure spiked up to the E-5s, then it immediately started to go down, now it is already at ~3E-7 (the initial value was ~1E-7).
So, the valve was closed and blanked off, therefore it wasn't stored appropriately, thus at the next opportunity (when the X-manifold will be vented), it will be removed, and blanked off.
Images attached to this report
Comments related to this report
janos.csizmazia@LIGO.ORG - 10:40, Thursday 17 April 2025 (83971)
The handler of this valve was torqued, and the pressure in the X-manifold fell to 8.14E-8 Torr, and it is seemingly stabilized. Before poking with this valve, the pressure was 1.04E-7 Torr (and still rising), so there was indeed a leak from this valve to the system, as this torquing means ~20% reduce in gas load.
We do a comprehensive leak check on the X-manifold during the rest of the week, so this valve with all adjacent flanges will be bagged and leak checked.
We are also considering putting an adapter on the valve instead of a blank, and pump it down, so the lower pressure in the outer side of the valve could help, if there is still some communication between the valve and the system - but of course, it depends on the result of the leak check.

Finally, the handler of this valve was LOTO-d - it was simply taken off, so there will be no accidental moving of this valve anymore.
Images attached to this comment
H1 CAL (CAL, CDS)
joseph.betzwieser@LIGO.ORG - posted 09:45, Wednesday 16 April 2025 - last comment - 10:05, Wednesday 16 April 2025(83949)
Beginning update of installed pydarm code
I'm following the pydarm deployment instructions here, to update the LHO pydarm install.

This is the 20250416.0 tag for pydarm (found here), and located at /ligo/groups/cal/pydarm/20250416.0

This is not the default cds conda environment, but the default you get when typing pydarm at a command line, or specifically invoking by running "conda activate /ligo/groups/cal/conda/pydarm".

This release has several fixes, the two most relevant to users being a permission issue when trying to commit and upload pydarm reports generated by a different user, and the second having a repport marked as an epoch boundary (i.e. for example when the sensing has changed significantly and don't want to combine prior sensing measurements in a different IFO state) be respected in the report itself - a bug had it still pulling in data from the previous epoch, although later reports saw the epoch boundary fine.

This should take 15 minutes or so.
Comments related to this report
joseph.betzwieser@LIGO.ORG - 10:05, Wednesday 16 April 2025 (83950)
This install has completed.  Passed a few quick tests, so looks successful to me.
LHO VE
jordan.vanosky@LIGO.ORG - posted 09:37, Wednesday 16 April 2025 (83947)
Morning Purge Air Checks 4-16-25

Morning dry air skid checks, water pump, kobelco, drying towers all nominal.

Dew point measurement at HAM1 , approx. -42C

Images attached to this report
H1 General
anthony.sanchez@LIGO.ORG - posted 07:41, Wednesday 16 April 2025 (83944)
Wednesday Engineering Mornin'

TITLE: 04/16 Day Shift: 1430-2330 UTC (0730-1630 PST), all times posted in UTC
STATE of H1: Planned Engineering
OUTGOING OPERATOR: None
CURRENT ENVIRONMENT:
    SEI_ENV state: MAINTENANCE
    Wind: 12mph Gusts, 8mph 3min avg
    Primary useism: 0.03 μm/s
    Secondary useism: 0.31 μm/s
QUICK SUMMARY:

Beautiful morning to ya, we've got lots of activies to do today!

Overflow from yesterday's work that may be need to be finished?

H1 SUS
edgard.bonilla@LIGO.ORG - posted 17:17, Tuesday 15 April 2025 - last comment - 12:26, Wednesday 16 April 2025(83940)
In air measurements for PR3 and SR3 OSEM calibration using the ISI

Edgard, Oli

We took measurements to get the above-resonance OSEM response of the PR3 and SR3 suspensions to characterize the gaines. This is a follow up to the in vacuum measurements on 80863, and to the estimated calibrations from 83605.

For PR3, the measurements were taken with 

- all of the M1 damping loops at a gain of -0.2 (instead of the nominal -1).
-The coil driver filter in state 1 (similar to the measurements that Jeff took).
- The ISI state was ISOLATED, but HEPI is locked, so we circumvented guardian by sliding off the Isolation Gain on HEPI. This should not affect the measurements for the OSEM calibration.

The results are saved in:
/ligo/svncommon/SusSVN/sus/trunk/HLTS/H1/PR3/Common/Data/

         2025-04-15_1431_H1ISIHAM2_ST1_WhiteNoise_PR3SusPoint_L_0p02to50Hz.xml
         2025-04-15_1431_H1ISIHAM2_ST1_WhiteNoise_PR3SusPoint_T_0p02to50Hz.xml
         2025-04-15_1431_H1ISIHAM2_ST1_WhiteNoise_PR3SusPoint_V_0p02to50Hz.xml

The similarly named _tf.txt files are stored in the same folder, and they export the measured M1 transfer functions using the [ L T V R P Y ] order.

Comments related to this report
oli.patane@LIGO.ORG - 17:26, Tuesday 15 April 2025 (83941)SEI

SR3 Measurements:

  • all of the M1 damping loops at a gain of -0.2 (instead of the nominal -0.5)
  • The coil driver filter in state 1
  • SEI state was ISOLATED, but HEPI is locked, so we circumvented guardian by sliding off the Isolation Gain on HEPI

I had a hard time trying to take data at first (no matter the excitation amplitude we were seeing no movement on the ISI sensors), and we figured out that it was because the SUSPOINT matrix for HAM5 ISI had never been populated! We found the correct matrix values in $(USERAPPS)/isc/common/projections/ISI2SUS_projection_file.mat as ISI2SUSprojections.h1.sr3.EUL2CART, and used /ligo/svncommon/SeiSVN/seismic/Common/MatlabTools/fill_matrix_values.m to fill them in. Then I was able to run the transfer functions.

Data files can be found at /ligo/svncommon/SusSVN/sus/trunk/HLTS/H1/SR3/Common/Data/2025-04-15_2100_H1ISIHAM5_ST1_WhiteNoise_SR3SusPoint_{L,T,V}_0p02to50Hz.xml, and have been committed to svn as r12227.

oli.patane@LIGO.ORG - 10:31, Wednesday 16 April 2025 (83954)

This morning we decided to do the rest of the DOFs for the SUSPOINT to M1 measurements of PR3 and SR3.

For SR3:

Same setup as before:

  • all of the M1 damping loops at a gain of -0.2 (instead of the nominal -0.5)
  • The coil driver filter in state 1
  • SEI state was ISOLATED, but HEPI is locked, so we circumvented guardian by sliding off the Isolation Gain on HEPI

Data files can be found at /ligo/svncommon/SusSVN/sus/trunk/HLTS/H1/SR3/Common/Data/2025-04-15_2100_H1ISIHAM5_ST1_WhiteNoise_SR3SusPoint_{R,P,Y}_0p02to50Hz.xml, and have been committed to svn as r12232.
 

edgard.bonilla@LIGO.ORG - 12:26, Wednesday 16 April 2025 (83955)

For PR3:

Same setup as before:

  • all of the M1 damping loops at a gain of -0.2 (instead of the nominal -0.5)
  • The coil driver filter in state 1
  • SEI state was ISOLATED, but HEPI is locked, so we circumvented guardian by sliding off the Isolation Gain on HEPI

Data files can be found at /ligo/svncommon/SusSVN/sus/trunk/HLTS/H1/PR3/Common/Data/2025-04-15_1431_H1ISIHAM5_ST1_WhiteNoise_SR3SusPoint_{R,P,Y}_0p02to50Hz.xml, and have been committed to svn as r12249.

H1 SUS
oli.patane@LIGO.ORG - posted 17:11, Tuesday 15 April 2025 - last comment - 17:32, Wednesday 16 April 2025(83939)
New SR3 Top2Top TFs with damping loops on

Back in August 2023 the damping gains for SR3 were reduced from -1 down(up?) to -0.5 to help with noise in DARM (72130). Since that change, we had never taken a set of transfer functions with the damping loops on with these new gains, so today I took those. The resulting transfer functions don't show too much damping, which is expected.

The data can be found in ../HLTS/H1/SR3/SAGM1/Data/2025-04-15_2000_H1SUSSR3_M1_WhiteNoise_{L,T,V,R,P,Y}_0p01to50Hz.xml, and has been committed to svn as r12228.

The results can be found in ../HLTS/H1/SR3/SAGM1/Results/ as 2025-04-15_2000_H1SUSSR3_M1_ALL_TFs.pdf and 2025-04-15_2000_H1SUSSR3_M1.mat, and have been committed to the svn as r12229.
 

Non-image files attached to this report
Comments related to this report
oli.patane@LIGO.ORG - 17:17, Wednesday 16 April 2025 (83963)

Linking analysis pdf showing cross coupling between all DOFs

Non-image files attached to this comment
oli.patane@LIGO.ORG - 17:32, Wednesday 16 April 2025 (83964)

Also adding a comparison between this measurement and the last time that we took damped transfer functions since those previous measurements would have been taken with a different set of damping gains.

The last time a damped measurement was taken was back in 2015, and those transfer functions look a lot different than the model and this recent measurement, so I also looked at the next previous damped measurement, from 2014. This one was in phase 2b, so not in chamber, but here at least we see that these damped measurements match up pretty well both with the model and with the recent measurement.

This PDF along with a zoomed in version of some of the plots can be found at /ligo/svncommon/SusSVN/sus/trunk/HLTS/Common/Data/ as

     allhltss_DampingOnComparison_H1SUSSR3_M1_Apr25vsFeb15vsMar14_ALL_TFs.pdf

     allhltss_DampingOnComparison_H1SUSSR3_M1_Apr25vsFeb15vsMar14_ALL_ZOOMED_TFs.pdf

and have been committed as r12251.

Non-image files attached to this comment
H1 General
anthony.sanchez@LIGO.ORG - posted 16:49, Tuesday 15 April 2025 (83935)
Tuesday Maintenance Day Report

TITLE: 04/15 Day Shift: 1430-2330 UTC (0730-1630 PST), all times posted in UTC
STATE of H1: Planned Engineering
INCOMING OPERATOR: None
SHIFT SUMMARY:
ISI is installed , but more work need to be completed before Optics can be installed.
PSL & SPI team are still in the PSL & anti Room, they have installed a beam splitter nut more work may be required.
Jason setup some Faro equipment.
Vacuum team started to pump down the BSC8 annulus door volume.

LOG:

Start Time System Name Location Lazer_Haz Task Time End
14:32 FAC Randy LVEA N HAM1 Heavy lift Prep 13:32
14:33 FAC Kim & Nellie LVEA N Technical Cleaning & Supplies, Kim Out early 16:25
14:54 FAC Eric LVEA N Checking HVAC zone conditions 14:57
15:02 FAC Eric End X N Replacing Sensor 15:43
15:17 FAC Christina Staging N Moving Folklifts & matierals 16:17
15:32 Safety Richard LVEA N Settign up HAM1 Work Cam 16:54
15:33 VAC Jordan LVEA N Purge Air Checks. 16:01
16:06 EE Marc CER N Getting chassis for testing. 16:09
16:11 EE Marc EX & Y N Power supply testing 17:25
16:15 VAC Travis & Jordan LVEA N Closing GV7 and pump work 17:15
16:22 SPI Jeff, Jason, Sina, RyanS, Josh optics Lab , PSL Yes Installing SPI Optics, Jeff Out Early 19:20
16:24 SUS Camilla & Matt HAM5 N Pulling off First Contact off optics 16:53
16:41 SAFE T McCarthy LVEA N Running parts and Safety checks 18:56
16:42 SEI Betsy LVEA N Running parts 20:28
16:49 FAC Nellie Mid X N Tech cleaning 17:20
16:54 SEI Jim, Randy Mitchell, TJ LVEA N SEI Crew flying in an ISI 18:07
17:20 FAC Kim MY N Technical Cleaning 18:35
17:24 ISC Dainel LVEA N verifing Equipment in the ISC racks 20:06
17:30 FAC Eric PSL adjacent N Talking to Jason. 18:12
18:04 VAC Jordan LVEA N Preping Y arm RGA 20:00
18:09 VAC Travis BSC8 N Checking the anulus pump by ITMY 18:16
18:21 FAC Christina Water tank area & Recycling   Forklifting & dump run 19:19
18:21 AOS Camilla, Matt LVEA N Pulling off first contact by HAM5 18:51
18:58 SEI Jim, TJ, Tyler, Randy, Mitchell LVEA HAM1 N ISI Installation 00:58
18:59 SEI Brian LVEA HAM1 N Watching HAM1 Installation. 21:03
19:51 Safe T Richard LVEA N Safety checks. 23:06
20:09 VAC Jordan LVEA N Pump & RGA checks & bake out 22:54
20:14 PSL & SPI Ryan S, Josh, Sina PSL YES Installing SPI Pickoff of the ALS pickoff. 00:14
20:16 ISC Camilla & Matt HAM5&6 N cleaning parts 23:49
20:46 PCAL Tony PCal Lab N Delivery 20:50
21:09 ISI Betsy LVEA N Checking on the ISI team 22:37
21:33 VAC Travis LVEA N Table sneaking 21:49
21:40 IAS Jason West bay N Staging Faro Equipment 23:40

 

Images attached to this report
H1 SEI
jim.warner@LIGO.ORG - posted 16:34, Tuesday 15 April 2025 - last comment - 07:56, Wednesday 16 April 2025(83936)
HAM1 ISI is in the chamber

It was a long day, but the HAM1 ISI is in the chamber. Mitch pointed out first thing this morning that the install fixture was still in the "short" configuration, with 2" spacer pads on the under side of the middle stand. We partially disconnected the I beams an swapped to the "tall" configuration, squared the I beams up to the chamber, including checking the height of the feet (procedure says 3", but could vary), centering on the HEPI piers with a plumb bob, checking I beam level with a bubble level and checking the vertical gap between the tightest point between the I beams and the chamber door, which the procedure recommended be 1.5". We then brought the ISI container into the LVEA, then realized the pallet jack was too close to the container to open the latches for the lid. We put the container on cribbing, adjusted the pallet jack then took lunch. After lunch, we took the lid off the can, flew the ISI over to the install cart by HAM1 and made a first attempt to slide the ISI in, at which point we realized the Stage 0 of the ISI would hit the tips of the HEPI springs. After much deliberation, we set the ISI back down on the cart and used the crane to lift the install fixture (I beams and stands) and extended the padded feet as muc has possible. We had to use the fork lift on the -Y side of the chamber, as the clean room blocked crane access. Clearance between the outside edge of the I beam and door was now about .5" and the feet were 4" above the floor. At this point the ISI sailed over the HEPI springs and we were able to proceed with the ISI install as normal, smooth sailing. 

First two photos show the height of the feet and the clearance between the I beams and the chamber. Last one shows the clearance through receiving with the container, as we brought the ISI in. Others got pictures of other points and I hope will add. 

We still have to pull the install fixture, then we can start plugging stuff in.

Images attached to this report
Comments related to this report
betsy.weaver@LIGO.ORG - 16:47, Tuesday 15 April 2025 (83937)
Months of build and testing, weeks-days of prep, 1 min 41sec to slide into chamber.  In like Flynn.
Images attached to this comment
betsy.weaver@LIGO.ORG - 07:56, Wednesday 16 April 2025 (83942)
Movie is too large so on One Drive:

https://caltech.box.com/s/5p1eysbye8tmq2177x40tera254ezpl4

Good job Jim, Mitchell, TJ, Tyler, and the illusive Randy on the forklift (not shown)!
Images attached to this comment
corey.gray@LIGO.ORG - 23:06, Tuesday 15 April 2025 (83943)EPO

Woo Woo!  Awesome job!  Tagging EPO for photos.

H1 PSL (ISC, SQZ)
jeffrey.kissel@LIGO.ORG - posted 16:03, Tuesday 15 April 2025 - last comment - 12:18, Wednesday 16 April 2025(83933)
SPI Pick-off Path Installation Begun
J. Kissel, S. Koehlenbeck, J. Oberling, R. Short, J. Freed
ECR E2400083
IIET 30642
WP 12453

After this morning's kerfuffle / belated power-outage recovery with the PSL HVAC system was resolved, Sina, Ryan, and Josh began the procedure we're walking thru outlined in Section 1 of T2500024. We're keeping running notes on the fly at the bottom of the google-doc for now.

In summary here, with more details to come, we got as far as 
- Clearing out some old IO equipment that unused and in the way of the SPI pick-off path
- Measuring the power around ALS-PBS01
- Installing the new ALS/SPI 80R/20T beam splitter
- Measuring the beam profile along the future SPI path, in reflection of this 80R/20T beam splitter.
Comments related to this report
jeffrey.kissel@LIGO.ORG - 08:48, Wednesday 16 April 2025 (83946)CSWG, SEI, SYS
Among the first things we did was measure the power at various places along the ALS beam path to get a good starting point. 

For the ~2W beams we used an Ophir 20C-SH (datasheet says accuracy of +/- 3%) and for ~100 mW beams we used a S401C, (datasheet says accuracy of +/- 7%). 

For laser safety, we would unlock the PMC and shutter the laser while we were placing these power meters, so I also kept track of the PMC TRANS to scale our measurements by input power appropriately.
We did NOT turn on the PMC's intensity stabilization servo (ISS), for no particular reason other than we forgot to turn it on for the first measurement, and then wanted to stay consistent. 
This meant that the PMC TRANS itself was slowly noise at that +0.5 [w] level, so my reported values below are "eyeball averages."

So, not exactly a NIST-level precision/accuracy setup, but good enough for sanity checks. As such, I'm not going to bother report uncertainty in the numbers below.

Here're the results (again, this is prior to doing anything to the path).
Times of measurements are all for 2025-04-15, and in UTC, such that trends of other PDs may be captured if need be.
    Location                               Power Meter [mW]         PMC Trans [W]       Time [UTC]
    (1) Going in to ALS-HWP2                   2060                    103.2              21:39     # expected: 2000 [mW]; good!
       (between ALS-L1 and ALS-HWP2)      

    (2) p-pol in trans of ALS-PBS01            1970                    102.8              22:17     # expected: 1950 [mW]; good!
        (between ALS-M2 and ALS-L2)          
    
    (3) s-pol in refl of ALS-PBS01               49.4                  103.2              21:44     # expected: 50 [mW]; good!
        (between ALS-L1 and ALS-M9)            
    
    (4) s-pol in refl of ALS-M9                  47.7                  103.0              21:48     # 44.9 [mW] reported by ALS-C_FIBR_EXTERNAL_DC_POWERMON, which is in trans of ALS-M9 at this time; good!
       (between ALS-M9 and ALS-FC2) 

All of these powers match expectation quite exquisitely. My guess for the inconsistency of (4) with the EXTERNAL monitor PD is that the beam splitter ratio of ALS-M9 programmed into the beckhoff calibration of the PD's channel is a bit off, but this can be cross-checked later.

We then installed SPI-BS1 (the 80R/20T BS), and cross-checked the reflectivity reported in LH0:83863.
    Location                               Power Meter [mW]         PMC Trans [W]       Time [UTC]
    (5) s-pol in refl of SPI-BS1                 37.7                  102.4              22:22

The PMC power is lower between (3) and (5), the input to the SPI-BS1 is different, so we need to scale the measurement a bit,
    Input Power to SPI-BS1 = 49.4 [mW] * (103.2 / 102.4) = 48.81 [mW]
    REFL power from SPI-BS1 = 37.7 [mW]
    
    Fractional reflection = 37.7 [mW] /  48.81 [mW] =  0.772 = 77%
    (from LHO:83863) = 77%.
Thus, our results today are consistent with what Josh and Keita measured in the optics lab.
jeffrey.kissel@LIGO.ORG - 12:18, Wednesday 16 April 2025 (83948)
Pictures from the work on 2025-04-15.

The first three attachments are without labels, just in case the pics are needed for something else in the future.

The diagram we were working with (from the SPI ECR) is also attached here for convenience.

The second three attachments *are* labeled, so I'll describe what happened using those.
20250415_some_optics_removed_labeled.jpg
- This is (mostly) the how the team started the day: with the area where the SPI pick-off path is intended to go full of un-diagrammed spare/unused stuff. I highlight red circles everything that was removed in this first attachment. Additionally, before the picture was taken, ALS-M8 and ALS-FC1 were removed and the temporary large vertical beam block was installed.

20259415_all_optics_removed_labeled.jpg
- This is the "after" all components cleared picture, and the table layout during the power measurements. As you can imagine, because of the lens tube on the SM1PD1A, there was no room between the PD and ALS-M9 to insert a power meter to measure the transmitted light  thru ALS-M9. As such, we can't validate the beam-splitting ratio of that optic. Ah well.

20250415_end_day_1_labeled.jpg
- This is how we left yesterday: We SPI-BS1 installed in its permanent location. Downstream, we sent the reflected beam into a WinCam head such that we could profile the beam incoming to the SPI path -- and assess whether we need lenses in order to adjust the beam size to match our fiber collimator. While we definitely saw the expected change in power and alignment at ALS-FC2, we elected to restore the power and alignment later.
Images attached to this comment
LHO VE (VE)
travis.sadecki@LIGO.ORG - posted 16:01, Tuesday 15 April 2025 - last comment - 16:08, Tuesday 15 April 2025(83932)
2025 April vent - VAC diary

Today's activities:

Comments related to this report
jordan.vanosky@LIGO.ORG - 16:08, Tuesday 15 April 2025 (83934)

CP1 RGA Bakeout - Ramped up to 100C. Will continue ramp up tomorrow. Please avoid this area inside of the caution tape

Images attached to this comment
H1 SUS
daniel.sigg@LIGO.ORG - posted 13:39, Tuesday 15 April 2025 (83930)
OpLev chassis in SUS-R1

There is an oplev chassis in SUS-R1 that isn't used for anything anymore. I powered it off and it will be removed soon.

H1 SUS
edgard.bonilla@LIGO.ORG - posted 10:11, Tuesday 15 April 2025 - last comment - 13:13, Tuesday 15 April 2025(83922)
Added an OSEM estimator folder to the sus SVN

Edgard, Oli, Brian.

We added a folder with a script that calculates the noise budget for the OSEM estimator for an HLTS.

The folder lives in: sus/trunk/HLTS/Common/FilterDesign/Estimator/.  

The script inside is called (at least for now) PR3_noise_budget.m, and it uses the simulink diagram in the same folder to run. The diagram doubles as a diagram for the estimator scheme itself, so it can be useful to look at.

We will post more commissioning scripts in this folder later in the week.

 

Comments related to this report
edgard.bonilla@LIGO.ORG - 13:13, Tuesday 15 April 2025 (83929)

Just ensured the noise budget runs in an operator machine. It needs access to the SusSVN, to the matlabtools folder of the SeiSVN, and access to the ISI2SUS projection matrices saved in /opt/rtcds/userapps/release/isc/common/projections/

The changes are current as of SusSVN revision 12226.

H1 CDS
david.barker@LIGO.ORG - posted 09:46, Tuesday 15 April 2025 - last comment - 15:09, Tuesday 15 April 2025(83921)
GV7 soft closed, alarms bypassed

Travis has asked for a temporary bypass on the GV7 cell phone alarms while this gate valve is soft closed

Bypass will expire:
Tue Apr 15 01:43:34 PM PDT 2025
For channel(s):
    H0:VAC-LX_GV7_ZSM179A_VALVE_ANIM
 

Images attached to this report
Comments related to this report
david.barker@LIGO.ORG - 15:09, Tuesday 15 April 2025 (83931)

Alarms has been reconfigured to expect GV7 to be soft closed.

Displaying reports 121-140 of 81651.Go to page Start 3 4 5 6 7 8 9 10 11 End