Morning dry air skid checks, water pump, kobelco, drying towers all nominal.
Dew point measurement at YBM , approx. -42C
Attached is the Trello showing what has been achieved this week and what is on the books for today. Many things started yesterday were (expectedly) not finished in 1 day so will roll to today, namely finishing feedthru (and some cable) population in the empty HAM1 chamber, and evaluating ITMY and it's reaction chain for closeout given the new CPY slight pitch change. The ISI is ~en route from the staging building to the LVEA ~today in prep for install early next week. Things seem to be on schedule with how I had them laid out in the plan, even after the Monday schedule loss due to the gnarly power outage and EE component failures which took the vent staff all day to recover from.
TITLE: 04/11 Day Shift: 1430-2330 UTC (0730-1630 PST), all times posted in UTC
STATE of H1: Planned Engineering
OUTGOING OPERATOR: None
CURRENT ENVIRONMENT:
SEI_ENV state: MAINTENANCE
Wind: 5mph Gusts, 3mph 3min avg
Primary useism: 0.02 μm/s
Secondary useism: 0.22 μm/s
QUICK SUMMARY:
Left over tasks from yesterday:
On the docket for today is:
BSC8 - Prep for Closeout
BSC8 - DOOR ON
HAM1 - Prep for ISI install
VAC Start Feedthru Swap
The IAS support tube survey will likely not happen as the recent power outage has seemingly damaged the FARO (specifically its external temperature sensor) and it needs to be seen by their service team. We are waiting to hear about a rental unit in the meanwhile.
Today's activities:
The new RF 5-way coax cable in the feedthrus are a little tight in the 5-way cross, but seemed to work ok. Also, the connections on the 4.5" feedthru port are a deep pocket connection so I was not convinced that the new connector was fully seated since you could not visually see it. Marc came out and checked continuity to settle my fears given the newness of this joint and the fact that we have many more to do. All good so far.
Picture of the completed D6 port on HAM 1, with new feedthrus and assembled five way cross extension.
Because of the tightness of the connectors when pushing the 4.5" feedthru into the D6b cross (namely the D6-5wx2 port), Fil and I checked for grounding on all of the ports/connections on this cross. All passed. Travis noted some tightness on the 5-way cross port 5wx4 on D1 opposite the chamber as well. So, Fil and I started checking these and indeed found a ground loop "fail" on both 25pins of the D1-5wx4 cross. We will try to swap in new style 25pin cables D2000456 which have entirely PEEK connector to see if that mitigates this. More to come in separate log.
WP 12451
The air RFPD cables were disconnected from the HAM1 feedthroughs (D6 and D5) and pulled back to ISC-R2. Cables were disconnected from the patch panels and removed from the rack. The air REFL WFS cables going to ISCT1 were removed, this included POPAIR_X. Daniel started installation of the new/modified patch panels in ISC-R2. The long RF cables will be re-terminated/labeled next week in the EE lab with female SMA connectors.
F. Clara, R. McCarthy, M. Pirello, D. Sigg
TITLE: 04/10 Day Shift: 1430-2330 UTC (0730-1630 PST), all times posted in UTC
STATE of H1: Planned Engineering
INCOMING OPERATOR: None
SHIFT SUMMARY:
Most things from today are either done or partially done.
LOG:
Start Time |
System |
Name |
Location |
Lazer_Haz |
Task |
Time End |
---|---|---|---|---|---|---|
14:00 |
FAC |
Kim, Nellie |
LVEA |
n |
Tech clean |
17:37 |
14:57 |
FAC |
Randy |
LVEA |
n |
Prepping for craning |
15:26 |
15:28 |
SEI |
Jim, Mitchell, TJ, Jennie |
LVEA |
n |
HAM1 Stack removal cont (TJ out 18:02, Mitchell,Jennie out 18:10) |
18:14 |
15:29 |
VAC |
Jordan |
LVEA |
n |
Purge air checks |
15:39 |
15:56 |
SEI |
Corey |
LVEA |
n |
Joining HAM1 SEI crew |
18:13 |
15:57 |
EE |
Fil |
OpticsLab |
n |
Making cables |
18:33 |
15:58 |
ISC |
Camilla |
LVEA |
n |
HAM1 optics checks |
18:00 |
16:00 |
Betsy, Robert, Tony, Sheila |
LVEA |
n |
CPY work |
18:16 |
|
16:14 |
EE |
Marc |
OpticsLab |
n |
Helping Fil with cables |
18:33 |
16:28 |
ISC |
Elenna |
LVEA |
n |
Joining Camilla |
18:00 |
16:55 |
Richard |
LVEA |
n |
Checking that everyone is working safely |
17:30 |
|
17:03 |
VAC |
Travis |
LVEA |
n |
Grapping parts |
18:25 |
17:09 |
VAC |
Jordan, Melina |
LVEA |
n |
Grabbing parts |
19:07 |
17:29 |
FAC |
Tyler, Erik |
Roof |
n |
Inspecting skylights |
17:34 |
18:34 |
EE |
Fil, Marc |
LVEA |
n |
Removing HAM1 cables |
19:48 |
18:52 |
HAM1 |
Camilla, Elenna |
LVEA & Optics Lab |
N |
Cleaning optics & getting parts |
19:24 |
19:08 |
FAC |
Nellie |
HAM Shack |
n |
Tech clean |
21:03 |
19:35 |
Jennie |
LVEA |
N |
Take care of used wipes |
19:54 |
|
19:35 |
Jennie |
OpticsLab |
n |
Putting wipes away |
19:45 |
|
19:35 |
VAC |
Travis |
LVEA |
n |
HAM1 cable work |
23:28 |
19:39 |
VAC |
Jordan, Melina |
LVEA |
n |
HAM1 cable work |
23:28 |
19:42 |
Tony, RyanC |
LVEA |
n |
BSC8 inventory |
20:51 |
|
19:47 |
FAC |
Randy |
LVEA |
n |
Craning |
21:44 |
19:54 |
EE |
Fil, Marc |
LVEA |
n |
Pulling more cables (Marc out 20:45) |
22:26 |
19:57 |
TJ |
LVEA |
n |
Dropping off stuff |
20:05 |
|
20:01 |
Betsy |
LVEA |
n |
HAM1 cable help |
20:44 |
|
20:05 |
ISC |
Josh, Keita, Jeff |
OpticsLab |
y(local) |
Testing SPI (Jeff out 22:04)(Keita out 23:43) |
23:51 |
20:14 |
ISC |
Camilla, Elenna |
LVEA |
n |
Continuing optics check |
22:17 |
20:27 |
Richard |
LVEA |
n |
Seeing Marc and Fil |
21:54 |
|
20:28 |
CDS |
Dave |
EY |
n |
Labeling a bad port |
21:28 |
21:08 |
Tony |
CER-ish, pcal lab |
n |
Putting box back |
21:13 |
|
22:26 |
Marc, Fil |
LVEA |
n |
Helping Betsy |
23:10 |
|
22:26 |
Betsy |
LVEA |
n |
Pulling cable help |
23:26 |
|
22:27 |
Richard |
LVEA |
n |
Checking in on everyone |
23:27 |
|
23:07 |
HAM1 |
Camilla & Elenna |
HAM1 |
N |
First contacting & optics cleaning |
23:42 |
Elenna, Camilla
We started to inspect the optics and beam dumps removed from HAM1 in 83836. They look dustier than expected, but after first contacting the optics are looking good, more to do...
The In-Vacuum RFPD cables needed for HAM1 were re-terminated. Connectors that mate to the feedthrough are the new 5-way coaxial connectors. The connector that connects to the PD was not modified. Total of 11 cables were re-terminated. Cables were tested for continuity and a TDR test was performed using the Keysight FieldFox Analyzer.
D1300278 Qty 7 length 156”
D1300278 Qty 4 length 106”
F. Clara, C. Gray, M. Pirello
The following cable serial numbers were modified, 4 short, 7 long:
S1301446 short
S1301447 short
S1301450 short
S1301458 short
S1301467 long
S1301468 long
S1301469 long
S1301470 long
S1301472 long
S1301473 long
S1301476 long
Images of cable modifications attached below:
This morning I ran a full IPMI sensor scan on all the realtime front ends and h1susauxex could only see one of its two redundant power supplies. I drove out to EX to inspect and found that both PS look fine with green LEDs. One at a time, I disconnected the power cord and pulled the PS out of the chassis, waited until the LED extinguished and then reinserted. This has made no change to the IPMI Sensor reporting. I'll flag this unit as an exception when reporting failed power supplies.
IPMI Sensor h1susauxex:
h1susauxex: OK | (2215) Chassis Intru | OK |
h1susauxex: OK | (2818) PS2 Status | Presence detected |
IPMI Sensor h1susauxey for comparison:
h1susauxey: OK | (2215) Chassis Intru | OK |
h1susauxey: OK | (2751) PS1 Status | Presence detected |
h1susauxey: OK | (2818) PS2 Status | Presence detected |
J. Kissel, O. Patane, I. Abouelfettouh, B. Weaver Betsy asked Ibrahim to gather some health check transfer functions in air prior to their CP work yesterday. He'd struggled for a bit to drive standard templates on the reaction chain, and called in re-inforcements. We reminded each other that "R0 tracking," or "L2 to R0 damping", or "the L2DAMP path" exists that uses the PUM (L2) OSEMs in feed back to the reaction chain (R0) to keep the chains moving together (ECR E2000011, built into all QUAD front-end models Jan 10 2020 LHO:54416, installed the next Tuesday LHO:54506, quickly and obviously became useful on the ETMs LHO:54556, but only turned on for the ITMs for the first time on Nov 10 2022 LHO:65728). It is *not* a DC coupled loop, it's an AC-coupled "velocity damping" controller, but it does have a giant amount of gain with a resgain filter right at 3.3 Hz. This tracking needs to be turned off during standard M0 or R0 "health check" transfer functions for *all* quads. They go unstable with huge (but standard health check) drive going to the main chain. We've run into having accidentally left these loops on for the ETMs before (LHO:60482), but this is the first time it's popped up for the ITMs, since it's the first time in a while we've characterized the ITMs. Anyways, we found it, turned the ITMY L2 to R0 damping/tracking OFF (ITMX remains ON), and the main and reaction chain TFs that Ibrahim gathered went without a hitch after turning it off. These TFs are /ligo/svncommon/SusSVN/sus/trunk/QUAD/H1/ITMY/SAGM0/Data/ 2025-04-09_1330_H1SUSITMY_M0_Mono_WhiteNoise_V_0p02to50Hz.xml 2025-04-09_1330_H1SUSITMY_M0_Mono_WhiteNoise_P_0p02to50Hz.xml 2025-04-09_1330_H1SUSITMY_M0_Mono_WhiteNoise_Y_0p02to50Hz.xml /ligo/svncommon/SusSVN/sus/trunk/QUAD/H1/ITMY/SAGR0/Data/ 2025-04-09_1800_H1SUSITMY_R0_WhiteNoise_V_0p02to50Hz.xml 2025-04-09_1800_H1SUSITMY_R0_WhiteNoise_P_0p02to50Hz.xml 2025-04-09_1800_H1SUSITMY_R0_WhiteNoise_Y_0p02to50Hz.xml Pressed for time, we did NOT take all DOFs. Just wanted to get these TFs mentioned in the aLOG.
Randy, Mitch, TJ, Jennie, Corey, Jim
This morning we pulled the rest of the HAM1 PISI. This part was relatively trouble free, masses stuck to the viton corks a bit, so we put a bit of tension on the chain bridle then tugged on the mass till it popped free. Masses, springs and hardware were kept clean, the support table and risers were set out on the floor. I think vac is up next with feedthrus, the ISI still has to be swapped to a different container in staging.
More pics of the absence of optics for EPO.
Thu Apr 10 10:11:06 2025 INFO: Fill completed in 11min 3secs
Morning dry air skid checks, water pump, kobelco, drying towers all nominal.
Dew point measurement at YBM , approx. -44C
TL;DR - Don't worry about the new models and screens in /userapps/trunk/sus - Brian is developing these for the OSEM estimator project and none of these are (currently) linked to any observatory model.
--
FYI - As part of the project to see if we can improve the noise caused by the OSEMs, we are developing new models and medm screens for the HLTS. Tracking for this ECR is in FRS ticket 32526.
We are running these at Stanford for testing, and putting them into userapps because we will be trying them on a triple at LHO soon (detail will be in a different log, they are still in flux a bit).
As such, I've created several new things in userapps. These are not linked to anything at either site - I'm putting this note here to reduce potential worry. These are still in development, so I suggest waiting a bit before you look at these.
New Files:
/userapps/trunk/sus/common/models/
HLTS_MASTER_W_EST.mdl - library part for M1 with the estimator calculation
SIXOSEM_T_STAGE_MASTER_W_EST.mdl - library part for upgraded HLTS model with the estimator included.
userapps/trunk/sus/common/medm/hxts/
SUS_CUST_HLTS_OVERVIEW_W_EST.adl - new overview screen with estimator
These files are copies of the existing parts as of March 2025, and I added _W_EST to the name of the copy.
userapps/trunk/sus/common/medm/estim/ - directory of new sub-screeens for the estimator
Updated files:
userapps/trunk/isi/common/models/
blend_switch_library.mdl - I added a new model to this library to allow smooth switching between the osem damping, the estimator damping, and OFF.
I'm running this from the new top-level model in
/userapps/trunk/isi/s1/s1suspr3.mdl
SVN update for Estimator models and screens - we should be ready to update SR3 at LHO
sus/common/models$ svn ci -m"new library part for a 1DOF estimator created. two are now in the SIX...MASTER_W_EST"
Adding ESTIMATOR_PARTS.mdl
Sending SIXOSEM_T_STAGE_MASTER_W_EST.mdl
Committed revision 31234.
sus/common/medm$ svn ci -m"updated estimator screens to be generic"
Sending estim/CONTROL_6.adl
Sending estim/ESTIMATOR_OVERVIEW.adl
Sending estim/FADE_CONTROL.adl
Sending estim/OSEM_SELECT.adl
Sending hxts/SUS_CUST_HLTS_OVERVIEW_W_EST.adl
Committed revision 31235.
NOTE - The estimator pulls pieces from sus/common/models, sus/common/medm AND isi/common/models (that is where the fader lives)
(I've also committed the top level model from Stanford - isi/s1/s1suspr3.mdl)